<strong>CIDCO</strong> <strong>OF</strong> MAHARASHTRA LTD<br />
C.A.No.03/<strong>CIDCO</strong>/EE(Elect)/2011-12 Sr. Page No.<br />
3.0 It is not the intent to specify herein all the details of design and<br />
construction of the equipment. However the equipment offered shall<br />
confirm in all respects to high standard of engineering design and<br />
workmanship. The installation of the infrastructure shall be executed in a<br />
neat manner and as per good engineering practices. The shop tests as<br />
well as pre-commissioning tests at site shall be conducted as per relevant<br />
IS and as per requirements of individual equipment as well as the set<br />
norms.<br />
4.0 The ratings, performance, testing at works, installation, testing at site,<br />
pre-commissioning checking and commissioning of all the equipment<br />
required shall conform to the latest revisions of all the relevant IS<br />
specifications.<br />
5.0 Site Conditions:<br />
All the equipments offered shall be suitable for following site conditions:-<br />
a) Maximum Temperature : 45 Deg. C<br />
b) Minimum Temperature : 6 Deg. C<br />
c) Design Ambient Temperature : 40 Deg. C<br />
d) Maximum Humidity : 96%<br />
e) Seismic Condition : As per IS 1893<br />
f) Atmosphere : Corrosive as found near as sea<br />
shore.<br />
5.1 The equipment to be supplied by the contractor shall be designed/<br />
suitable for following supply system.<br />
5.1.1 Voltage stepped down to 11KV<br />
Voltage : 11 KV<br />
Frequency : 50 Hz<br />
Fault level : 350 MVA