<strong>CIDCO</strong> <strong>OF</strong> MAHARASHTRA LTD<br />
C.A.No.03/<strong>CIDCO</strong>/EE(Elect)/2011-12 Sr. Page No.<br />
Ferrules shall be of self sticking type and shall be employher to designate<br />
the various cores of control cable by the terminal numbers to which the<br />
cores are connected for ease in identification and maintenance.<br />
3.4 Cable Glands<br />
Cable glands to be supplied shall be brass single/double compression type<br />
as per the directions of Engineer-in-charge. Generally single compression<br />
type cable glands shall be used for indoor protected locations and double<br />
compression type shall be used for outdoor locations.<br />
3.5 Cable Trays<br />
Prefabricated hot dip galvanized sheet steel cable trays shall be used for<br />
maximum support span of 2000 mm unless design is approved for larger<br />
span. For requirements of larger than 750 mm width two trays shall be<br />
run side by side. Cable trays shall be suitable for a cable weight of 50<br />
kg/m running length of tray. Minimum thickness of sheet steel/galvanized<br />
shall be 3 mm/86 micorns. Cable trays fabricated from standard rolled<br />
sections shall used 50 x 50 x 6 /ISMC 100 sections for runners for<br />
supporting spans limited to 2000 mm/more than 2000 mm respectively.<br />
Cross support shall be 32 x 6 mm flat 25 x 25 x 6 mm angle for widths<br />
upt o500 mm/ more than 500 mm respectively. If unit rate not included<br />
in schedule of rates then cable trays if required shall be<br />
fabricated/installed at site as per the per tonne rate for electrical<br />
structural supports etc.<br />
4.0 CABLE LAYING<br />
4.1 Cable network shall include power, control lighting cables, which shall be<br />
laid in trenches, cable trays or conduits as detailed in the relevant<br />
drawings and cable schedules. Erection of cable trays as required shall be<br />
the responsibility of the contractor. Cable routing shall be checked in the