and periodic replacement of switches and switch<br />

machines. Turnouts must be inspected and replaced<br />

frequently to protect against derailment. While<br />

minor defects in switch points and turnouts can be<br />

remedied with eld welding, their replacement over<br />

time is required to ensure reliable operations.<br />

PE 4633 RAIL, UPR<br />

This project provides for the replacement of rail<br />

on the Union Paci c Commuter Lines. Speci c<br />

locations are to be determined. In the course of<br />

installing the rail, a portion of the ties, ballast, and<br />

other track material is typically replaced as well. Rail<br />

replacement provides assurance of continued safe<br />

operations, reduction of maintenance costs, and a<br />

smoother, quieter ride for commuters.<br />

PE 4635 BRIDGE IMPROVEMENTS, BNSF<br />

PE 4636 BRIDGE IMPROVEMENTS, MET<br />

PE 4637 BRIDGE IMPROVEMENTS, UPR<br />

These projects fund the improvement of bridges<br />

along the BNSF Railway, the <strong>Metra</strong> system, and<br />

the Union Paci c commuter rail lines. These<br />

improvements can include such rehabilitation items<br />

as timber wingwalls and fencing, cracked bearing<br />

blocks, and cracked bridge seats on abutments.<br />

Speci c improvements will be determined based on<br />

a survey of eld conditions.<br />

PE 4640 BRIDGE FILL, Z92, MWD<br />

This project consists of removal of an existing bridge<br />

at the Chicago Gravel Company (M.P. 34.2) on the<br />

Milwaukee District West Line. The steel structure<br />

will be removed and will be replaced with earth<br />

ll. Utility lines will be relocated and/or modi ed as<br />

necessary.<br />

PE 4648 ROW FENCING, UPR<br />

This project consists of the materials and labor<br />

necessary to erect fencing along the railroad rightof-way<br />

on the Union Paci c commuter rail lines.<br />

Speci c locations are determined based on eld<br />

conditions and are subject to change in the course of<br />

consultation with local o cials.<br />

SIGNAL, ELECTRICAL and<br />

COMMUNICATIONS<br />

PE 2938 A-5 INTERLOCKER RENEWAL<br />

This project consists of the modernization and<br />

upgrade of the A-5 interlocker at Paci c Junction<br />

in Chicago, Illinois. This is the point where the<br />

Milwaukee district main line diverges into the West<br />

and North lines.<br />

Under this project, signal system components will be<br />

replaced. The interlocker control will be upgraded<br />

to a solid state system. Additionally, the control<br />

point will be shifted from the A-5 Tower to <strong>Metra</strong>’s<br />

Consolidated Control Facility (CCF) at 1501 S. Canal<br />

Street, Chicago.<br />

PE 3337 LAKE STREET INTERLOCKER, UPR<br />

This project consists of the modernization and<br />

upgrading of the Lake Street interlocker, at the north<br />

end of the Ogilvie Transportation Center (OTC). It will<br />

replace track, trackbed, switches, switch machines,<br />

switch heaters, dwarf signals, and signal cable for the<br />

remaining facilities. In addition, in a future year, the<br />

interlocking control machine in Lake Street Tower will<br />

be replaced by modern solid state equipment.<br />

59