PRESUPUESTO Y MEDICIONES<br />
Hostel<br />
CÓDIGO RESUMEN UDS LONGITUD ANCHURA ALTURA PARCIALES CANTIDAD PRECIO IMPORTE<br />
CAPÍTULO CHAPTER 7 ROOF<br />
07 01 m2 Inverted roof<br />
Flat roof, walkable and non-ventilated private use, inverted, with fixed floor consists of aerated concrete<br />
layer thickness between 2 and 30cm finished with a leveling layer of 1.5 cm waterproofing cement<br />
mortar plastering for slope formation, separating layer based on polyethylene film 0.50 mm thick<br />
monolayer waterproofing membrane by not bonded to the support constituted by a sheet of ethylene<br />
propylene diene monomer EPDM 1.5 mm thick separating layer based on polyethylene film of 0 ,<br />
50mm thick insulation panels consisting of extruded polystyrene (XPS) de100mm. thickness and K =<br />
0.027 W / m ° C, antipunzanante layer polyester felt made up of 300 g/m2, floor tile 20x10cm Catalan<br />
about 2.5 cm layer of cement mortar (1:6), including pre-cleaning of the support , stakeout, training<br />
bibs, mimbeles, sinks and other special reinforcing strips, overlaps, and wastage. Measured in horizontal<br />
projection.<br />
1 56,20 17,50 983,50<br />
983,50 97,08 95.478,18<br />
TOTAL CAPÍTULO CHAPTER 7 ROOF .................................................................................................................. 95.478,18<br />