Upstream activities are ramping up with land access, drilling and<br />

gas processing facilities tracking within plan<br />

• Participated in over 200 wells during the half<br />

• Two hybrid coil tubing drilling rigs now in operation; capability to<br />

drill wells in less than 4 days per rig; more rigs to be added<br />

progressively over the coming months<br />

• On track to drill 30 wells per month by mid <strong>2012</strong>, with up to 1,100<br />

new production wells expected to be drilled by the end of 2015 to<br />

support initial ramp requirements for two trains<br />

• Land access on schedule; 428 well locations scouted; land access<br />

plan ensures rigs minimise down-time<br />

• First Siemens electric drive compressor completed factory<br />

acceptance testing in January, on schedule<br />

• Plant module construction awarded to BJC Thailand – first module<br />

shipment due mid <strong>2012</strong>, on schedule<br />

• Gas processing and water treatment facilities construction on track<br />

to commence mid-<strong>2012</strong><br />

Milestones<br />

Date<br />

36 |<br />

First two Savanna rigs introduced mid 2011<br />

Initial drilling for Train 1 complete mid 2013<br />

Mechanical completion of first gas processing plant mid 2013<br />

Train 1 - gas processing plants complete late 2014<br />

First gas to LNG Train 1 early 2015