Upstream activities are ramping up with land access, drilling and<br />
gas processing facilities tracking within plan<br />
• Participated in over 200 wells during the half<br />
• Two hybrid coil tubing drilling rigs now in operation; capability to<br />
drill wells in less than 4 days per rig; more rigs to be added<br />
progressively over the coming months<br />
• On track to drill 30 wells per month by mid <strong>2012</strong>, with up to 1,100<br />
new production wells expected to be drilled by the end of 2015 to<br />
support initial ramp requirements for two trains<br />
• Land access on schedule; 428 well locations scouted; land access<br />
plan ensures rigs minimise down-time<br />
• First Siemens electric drive compressor completed factory<br />
acceptance testing in January, on schedule<br />
• Plant module construction awarded to BJC Thailand – first module<br />
shipment due mid <strong>2012</strong>, on schedule<br />
• Gas processing and water treatment facilities construction on track<br />
to commence mid-<strong>2012</strong><br />
Milestones<br />
Date<br />
36 |<br />
First two Savanna rigs introduced mid 2011<br />
Initial drilling for Train 1 complete mid 2013<br />
Mechanical completion of first gas processing plant mid 2013<br />
Train 1 - gas processing plants complete late 2014<br />
First gas to LNG Train 1 early 2015