Curtis Island site preparations are progressing well, and<br />

major downstream contracts have been awarded<br />

January <strong>2012</strong><br />

• Bechtel responsible for all activity on Curtis Island under a<br />

fixed price contract<br />

• Costs confirmed for key Train 2 contracts, including Bechtel<br />

EPC contract; long lead items awarded<br />

• Engineering, procurement and construction of Curtis Island<br />

and Mainland facilities approximately 12% complete<br />

• On budget and schedule for Train 1 start-up mid-2015<br />

• Roll-on roll-off facility complete, including required<br />

dredging works<br />

• LNG tank area site preparations on track; tank contractor<br />

mobilisation in March <strong>2012</strong><br />

• Curtis Island site camp on schedule for June <strong>2012</strong> operations<br />

Milestones<br />

Date<br />

38 |<br />

Complete 2015<br />

Commenced Curtis Island works mid 2011<br />

Awarded EPC contract to Bechtel mid 2011<br />

1st occupancy of Curtis Island camp mid <strong>2012</strong><br />

Heavy mechanical erection start late <strong>2012</strong><br />

First LNG module delivery early 2013<br />

Pre-commissioning late 2014<br />

Train 1 ready for start-up mid 2015