Curtis Island site preparations are progressing well, and<br />
major downstream contracts have been awarded<br />
January <strong>2012</strong><br />
• Bechtel responsible for all activity on Curtis Island under a<br />
fixed price contract<br />
• Costs confirmed for key Train 2 contracts, including Bechtel<br />
EPC contract; long lead items awarded<br />
• Engineering, procurement and construction of Curtis Island<br />
and Mainland facilities approximately 12% complete<br />
• On budget and schedule for Train 1 start-up mid-2015<br />
• Roll-on roll-off facility complete, including required<br />
dredging works<br />
• LNG tank area site preparations on track; tank contractor<br />
mobilisation in March <strong>2012</strong><br />
• Curtis Island site camp on schedule for June <strong>2012</strong> operations<br />
Milestones<br />
Date<br />
38 |<br />
Complete 2015<br />
Commenced Curtis Island works mid 2011<br />
Awarded EPC contract to Bechtel mid 2011<br />
1st occupancy of Curtis Island camp mid <strong>2012</strong><br />
Heavy mechanical erection start late <strong>2012</strong><br />
First LNG module delivery early 2013<br />
Pre-commissioning late 2014<br />
Train 1 ready for start-up mid 2015