Preparations for the major pipeline construction activities and gas<br />

field electrification project are on track<br />

• EPC pipeline contract awarded to McConnell Dowell,<br />

Consolidated Contracting Co. joint venture in July 2011<br />

• Line pipe awarded to MetalOne in Japan; first delivery<br />

made in January <strong>2012</strong><br />

• APLNG and QCLNG collaborating on Narrows crossing;<br />

execution by QCLNG delayed however significant float<br />

remains for APLNG<br />

• Pipeline land access arrangements progressing at rate<br />

which maintains pipeline construction productivity;<br />

agreements reached with one third of properties<br />

• Engineering on schedule and welding on track to<br />

commence in June <strong>2012</strong><br />

• Train 1 electrification contracts awarded to Powerlink<br />

and on schedule<br />

Milestones<br />

Date<br />

Line pipe manufacture 2011 and <strong>2012</strong><br />

Welding commences mid <strong>2012</strong><br />

Pipeline completion early 2014<br />

Train 1 electrification complete mid 2014<br />

37 |