As security deposit will be required to be submitted to the <strong>Municipality</strong> to guarantee<br />

compliance with the agreement requirements, and ensure the restoration and/or repair<br />

<strong>of</strong> any road damage. <strong>The</strong> amount <strong>of</strong> the deposit will be equal the cost to install the<br />

service.<br />

Haul routes will be identified and approved for inclusion in the development agreement<br />

with the municipality, prior to work commencing. <strong>The</strong> <strong>Municipality</strong> recommends that the<br />

Developer makes their best effort to plan haul routes that are primarily located on<br />

Provincial or County roads and limit the use <strong>of</strong> municipal roadways. <strong>The</strong> developer shall<br />

be responsible for the reasonable maintenance <strong>of</strong> the haul roads or roads used during<br />

construction, including dust control, grading, repairs, restoration to ensure a safe<br />

condition at all times, and so that the roads are able to support emergency service<br />

vehicles at all time.<br />

Prior to work commencing the developer shall mark the location <strong>of</strong> any services located<br />

on an unopened road allowance.<br />

Prior to work commencing the developer shall satisfy the <strong>Municipality</strong> with respect to<br />

liability insurance and shall save the <strong>Municipality</strong> harmless from any claim, loss, costs,<br />

damages or other expenses or any incidental or indirect claim arising from the project.<br />

5.2 Project Roads<br />

Provide comment on the proposed project’s plans respecting proposed road access<br />

Detailed engineered plans, including intersection details are required for each<br />

entrance/access to be installed. Plans will be approved by the Municipal engineer at the<br />

proponents cost prior to the commencement <strong>of</strong> construction.<br />

All entrances/accesses will be identified and subject to the development agreement.<br />

Final approval for all entrances will be subject to municipal operations considerations<br />

and By-laws.<br />

All transmission lines are to be buried underground in order to decrease the<br />

maintenance required to maintain the lines and to limit the amount <strong>of</strong> stray voltage that<br />

is present under and around high voltage overhead transmission lines. In addition the<br />

proponent should work with other companies proposing to install transmission lines by<br />

utilizing the same trench or by the sharing <strong>of</strong> lines in the same trench.<br />

Identify any issues and provide recommendations with respect to road access<br />

All access roads are to be signed that they are private roads. Signage is to be approved<br />

by the <strong>Municipality</strong>. Signage is to be installed at pre-construction phase.<br />