Competitive Power Ventures, Inc. - Energy Highway
Competitive Power Ventures, Inc. - Energy Highway
Competitive Power Ventures, Inc. - Energy Highway
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
CPV VALLEY ENERGY CENTER<br />
permits were not able to be issued. With SEQRA now complete, the other state permits are now able<br />
to be issued.<br />
The Project submitted a Full Environmental Assessment Form (EAF) on March 10, 2008, formally<br />
commencing the permitting process. Since that time, the Project has achieved many milestones and<br />
advanced the permitting of the Project to a point where it is now nearing completion. A complete list<br />
of permits and approvals, as well as their status can be provided upon request; however, the<br />
following is a brief summary of the key permits, approvals and their status.<br />
5.1 New York State Environmental Quality Review Act<br />
CPV Valley completed the NY SEQRA process earlier this month. CPV Valley began the SEQRA process<br />
on March 10, 2008 with the submittal of the EAF, and has advanced through the process with the<br />
Town of Wawayanda Planning Board acting as Lead Agency. Most recently on May 23, 2012, the Lead<br />
Agency passed a unanimous board resolution adopting the Findings Statement for the CPV Valley<br />
<strong>Energy</strong> Center. This was the final step in the SEQRA process and allows other state entities to issue<br />
their respective permits associated with the Project.<br />
5.2 Air Permit<br />
CPV Valley is subject to the Clean Air Act’s requirement for a Prevention of Significant Deterioration<br />
(PSD) permit review. The Project submitted an application for regulatory agency review in conjunction<br />
with the Federal and State PSD and non-attainment new source review requirements and process.<br />
The New York State Department of Environmental Conservation (DEC) is reviewing the application as<br />
the Environmental Protection Agency (EPA) has delegated DEC the responsibility for reviewing and<br />
administering permits in the State of New York. DEC is currently in the process of drafting the air<br />
permit.<br />
5.3 Wetlands Permit<br />
CPV Valley has submitted an application for a Joint Wetlands Permit to the DEC and the U.S. Army<br />
Corps of Engineers (ACOE). On May 9, 2012 the ACOE determined the application to be complete and<br />
commenced the 45 day review period. The DEC has completed the review of their portion of the<br />
application and has drafted the permit, which is expected to be issued by the DEC shortly.<br />
Great effort was taken in the design and layout of the facility to minimize impacts to wetlands. As a<br />
result, the Project will have a permanent impact less than 0.50 acres; therefore only a Nationwide<br />
Permit is required.<br />
5.4 Certificate of Public Convenience and Necessity<br />
On November 14, 2010, CPV Valley filed a Petition with the New York PSC for approval of a lightened<br />
regulatory regime and financing in connection with a natural gas electric generating facility and was<br />
assigned case number 10-E-0501. On November 24, 2010 the New York PSC issued a notice under<br />
New York's Administrative Procedures Act, calling for public comments on CPV's Petition. The public<br />
comment period was open for forty-five (45) days and closed on January 10, 2011 without any<br />
comments. CPV Valley has provided a supplement to the PSC, highlighting aspects of the project that<br />
are more defined than they were at the time of the November 14, 2010 submittal. Upon issuance of<br />
the Findings Statement by the Lead Agency under SEQRA, the PSC will be in a position to issue their<br />
Findings Statement related to the Petition.<br />
5.5 New York Independent System Operator Interconnect Process<br />
CPV Valley submitted an Interconnection Application to the NYISO on July 5, 2007 and was assigned<br />
queue position #251. CPV Valley has completed the Feasibility Study, System Reliability Impact Study<br />
and the Facilities Study as a member of Class Year 2009. The Project subsequently entered Class Year<br />
2011, which is the current Facilities Study underway at the NYISO. Upon completion of the Class Year<br />
New York <strong>Energy</strong> <strong>Highway</strong><br />
9 | P age