30.04.2014 Views

Competitive Power Ventures, Inc. - Energy Highway

Competitive Power Ventures, Inc. - Energy Highway

Competitive Power Ventures, Inc. - Energy Highway

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

1.4 Potable Water and Sewer<br />

CPV VALLEY ENERGY CENTER<br />

CPV Valley will interconnect with the exiting Town of Wawayanda Sewer and Water systems, both<br />

located adjacent to the Project site along Route 6. The interconnecting pipes will be located in existing<br />

ROW along Route 6. CPV Valley is working closely with DOT and in the process of obtaining the<br />

necessary approvals.<br />

1.5 Gas Interconnect<br />

The easements required to interconnect the Project with Millennium will be obtained by Millennium.<br />

Millennium has identified various routes that maximize existing utility and railroad ROW, while<br />

minimizing impacts to private landowners. These routes identified by Millennium range from 7 to 8<br />

miles in length.<br />

2.0 Projected In-Serve Date and Project Schedule<br />

CPV Valley could be in-service in the first quarter of 2016 if the Project were awarded a contract by no<br />

later than October 2012. The project permitting is anticipated to be complete by the summer of<br />

2012, and the NYISO interconnection process is projected to be complete with an Interconnection<br />

Agreement executed in the fall of 2012. With the permitting complete, an executed Interconnection<br />

and an executed long-term revenue contract by October 2012, CPV Valley could achieve an in-service<br />

date in early 2016. As discussed previously, financing of CPV Valley is contingent on the long-term<br />

revenue contract. Therefore, any projected in-service date will be driven by when the long-term<br />

contract is executed. A preliminary project schedule is provided in Appendix C – Preliminary Project<br />

Schedule.<br />

3.0 Interconnection<br />

3.1 Interconnection Point<br />

The Point of Interconnection (POI) for CPV Valley is a new gas insulated switchgear (GIS) substation to<br />

be located in Middletown, New York along NYPA’s 345kV Marcy South line #42 between Coopers<br />

Corners and Rock Tavern substations (NYISO Zone G). The specific location is shown in Appendix E –<br />

Point of Electrical Interconnection. This location was studied by the NYISO and NYPA representatives<br />

throughout the NYISO interconnection process.<br />

3.2 POI Assessment<br />

As discussed above, the POI location was studied by the NYISO and NYPA representatives for technical<br />

feasibility and approved in the Class Year 2009 Facility Study process. The interconnection consists of<br />

an underground cable from the Project to a new GIS substation, to be constructed by the Project,<br />

located directly adjacent to the existing NYPA ROW. Interconnecting at this location had several<br />

positive attributes described below:<br />

Close Proximity to the Project site – The relatively short distance between the POI and the Project<br />

helped mitigate any potential environmental impacts associated with the transmission line connecting<br />

the Project to the grid. The close proximity of site (less than one mile) to the POI eliminated the<br />

potential uncertainty associated with additional approvals required for transmission lines in excess of<br />

one mile.<br />

Utilization of Existing ROW – The interconnection route to the POI utilizes mostly Project property<br />

and existing state ROW. Only a small amount of private land was needed to facilitate the<br />

interconnection. To eliminate any uncertainty associated with the interconnection route, CPV<br />

procured the necessary easements from the private landowner in 2008.<br />

Capacity of Marcy South – Interconnection to Marcy South provides a significant amount of<br />

generation to the Lower Hudson Valley. As determined by NYISO in the interconnection process, the<br />

New York <strong>Energy</strong> <strong>Highway</strong><br />

11 | P age

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!