1.4 Potable Water and Sewer<br />
CPV VALLEY ENERGY CENTER<br />
CPV Valley will interconnect with the exiting Town of Wawayanda Sewer and Water systems, both<br />
located adjacent to the Project site along Route 6. The interconnecting pipes will be located in existing<br />
ROW along Route 6. CPV Valley is working closely with DOT and in the process of obtaining the<br />
necessary approvals.<br />
1.5 Gas Interconnect<br />
The easements required to interconnect the Project with Millennium will be obtained by Millennium.<br />
Millennium has identified various routes that maximize existing utility and railroad ROW, while<br />
minimizing impacts to private landowners. These routes identified by Millennium range from 7 to 8<br />
miles in length.<br />
2.0 Projected In-Serve Date and Project Schedule<br />
CPV Valley could be in-service in the first quarter of 2016 if the Project were awarded a contract by no<br />
later than October 2012. The project permitting is anticipated to be complete by the summer of<br />
2012, and the NYISO interconnection process is projected to be complete with an Interconnection<br />
Agreement executed in the fall of 2012. With the permitting complete, an executed Interconnection<br />
and an executed long-term revenue contract by October 2012, CPV Valley could achieve an in-service<br />
date in early 2016. As discussed previously, financing of CPV Valley is contingent on the long-term<br />
revenue contract. Therefore, any projected in-service date will be driven by when the long-term<br />
contract is executed. A preliminary project schedule is provided in Appendix C – Preliminary Project<br />
Schedule.<br />
3.0 Interconnection<br />
3.1 Interconnection Point<br />
The Point of Interconnection (POI) for CPV Valley is a new gas insulated switchgear (GIS) substation to<br />
be located in Middletown, New York along NYPA’s 345kV Marcy South line #42 between Coopers<br />
Corners and Rock Tavern substations (NYISO Zone G). The specific location is shown in Appendix E –<br />
Point of Electrical Interconnection. This location was studied by the NYISO and NYPA representatives<br />
throughout the NYISO interconnection process.<br />
3.2 POI Assessment<br />
As discussed above, the POI location was studied by the NYISO and NYPA representatives for technical<br />
feasibility and approved in the Class Year 2009 Facility Study process. The interconnection consists of<br />
an underground cable from the Project to a new GIS substation, to be constructed by the Project,<br />
located directly adjacent to the existing NYPA ROW. Interconnecting at this location had several<br />
positive attributes described below:<br />
Close Proximity to the Project site – The relatively short distance between the POI and the Project<br />
helped mitigate any potential environmental impacts associated with the transmission line connecting<br />
the Project to the grid. The close proximity of site (less than one mile) to the POI eliminated the<br />
potential uncertainty associated with additional approvals required for transmission lines in excess of<br />
one mile.<br />
Utilization of Existing ROW – The interconnection route to the POI utilizes mostly Project property<br />
and existing state ROW. Only a small amount of private land was needed to facilitate the<br />
interconnection. To eliminate any uncertainty associated with the interconnection route, CPV<br />
procured the necessary easements from the private landowner in 2008.<br />
Capacity of Marcy South – Interconnection to Marcy South provides a significant amount of<br />
generation to the Lower Hudson Valley. As determined by NYISO in the interconnection process, the<br />
New York <strong>Energy</strong> <strong>Highway</strong><br />
11 | P age