2011 Facilities Study, the Project will be capable of advancing towards execution of an<br />

Interconnection Agreement.<br />

5.6 Site Plan and Special Use<br />

CPV VALLEY ENERGY CENTER<br />

CPV Valley is required to obtain a Site Plan approval and Special Use permit from the Town of<br />

Wawayanda. An application for Site Plan approval and Special Use was submitted on [date] to the<br />

Town of Wawayanda Planning Board. The plans have periodically been modified to reflect the most<br />

current design and also to coincide with the determinations of the Final Environmental Impact<br />

Statement (EIS) developed during the SEQRA approval process. Upon issuance of a Findings Statement<br />

by the Lead Agency, the Site Plan permit and approval and Special Use permit will be finalized.<br />

C. ADDITIONAL INFORMATION<br />

1.0 Property<br />

CPV Valley has obtained site control for the project site and is securing the remaining easements for<br />

the electrical transmission and water line from the state, which could not be obtained until SEQRA<br />

was complete. A brief description of the real estate (project site as well as laterals) and status are<br />

provided below.<br />

1.1 Project Site<br />

CPV Valley controls the 122 acre Project site located in the Town of Wawayanda, Orange County, New<br />

York. The Project site is currently undeveloped land, which a portion of was previously used for<br />

agricultural purposes and a portion is wooded area. The property is bound by an interstate highway<br />

(I-84) and New York State Roadways (Route 6 and Route 17M). This Route 6 corridor has been<br />

identified by the Town for commercial development, and is zoned as such, Mixed Commercial. Please<br />

refer Appendix B for an aerial overview of the Project site.<br />

1.2 Electrical Interconnect<br />

The electrical interconnect with NYPA’s existing 345kV electric transmission line (Line 42) is less than<br />

one mile from the project site. The property required to allow the Project to interconnect at the Point<br />

of Interconnection (POI), consists of a private easement and use of existing rights of way controlled by<br />

the state. CPV Valley secured the necessary easement area from the private landowner in 2008 and is<br />

coordinating with the New York State Department of Transportation (DOT) to utilize the existing DOT<br />

ROW along Route 17M for the underground electric transmission lines connecting the Project to<br />

NYPA’s Marcy South transmission line. To facilitate the interconnection, the Project will construct a<br />

new substation on private property adjacent to NYPA’s ROW. CPV has obtained the construction and<br />

permanent easements to allow for the construction and operation of the 80’ x 50’ substation. The<br />

area surrounding the interconnection is developed commercial property.<br />

1.3 Water Supply and Discharge<br />

Consistent with CPV’s ongoing commitment to the environment, CPV Valley will be utilizing the<br />

treated water (gray water) currently being discharged by the City of Middletown’s (City) waste water<br />

treatment facility. This use of gray water eliminates the need to use New York’s potable water<br />

resources for an industrial process. In addition to the purchase of the City’s gray water, the Project<br />

will send its wastewater to the City’s treatment facility. The waterlines associated with the supply<br />

and discharge water will be located within existing ROW along Route 17M and are approximately 1.5<br />

miles in length. CPV Valley is working closely with the DOT and is in the process of obtaining the<br />

necessary approvals.<br />

New York <strong>Energy</strong> <strong>Highway</strong><br />