21.05.2014 Views

Arrow Prospectus - PGS

Arrow Prospectus - PGS

Arrow Prospectus - PGS

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

ARROW SEISMIC ASA – INITIAL PUBLIC OFFERING<br />

14. LEGAL MATTERS<br />

14.1 DISPUTES<br />

<strong>Arrow</strong> is involved in a dispute in connection with the conversion of Geo Atlantic (ex Polar King) at Drammen<br />

Skipsreparasjon AS (“DSR”). Geo Atlantic was severely delayed and the conversion contract was cancelled by<br />

<strong>Arrow</strong> in the autumn of 2006. DSR disputed <strong>Arrow</strong>’s right to cancel the conversion contract and tried to prevent<br />

Geo Atlantic from leaving the yard. <strong>Arrow</strong> had to bring the matter to court in order to allow Geo Atlantic to sail.<br />

The Company was successful and awarded costs. However DSR was entitled to a guarantee for its alleged<br />

outstanding against <strong>Arrow</strong> and arbitration proceedings has been initiated against <strong>Arrow</strong> in Norway. The claim is<br />

about NOK 38.4 million. <strong>Arrow</strong> is disputing the claim, and is represented by Wikborg, Rein who is presently<br />

working on the points of defence. <strong>Arrow</strong> has raised a counterclaim of about NOK 13.5 million for the extra costs<br />

incurred by <strong>Arrow</strong> as a consequence of the breach of contract by DSR, as Geo Atlantic had to be taken over in an<br />

unfinished condition, and the work was finished at Gøtaverken in Sweden. The hearing in the arbitration will<br />

take place in June 2007.<br />

14.2 MATERIAL CONTRACTS<br />

14.2.1 Acquisition of new buildings 532, 533, 534, and 535<br />

ASI II has entered into a Spanish tax lease structure for the construction and acquisition of newbuilding 532. ASI<br />

III, ASI V, and ASI VI have entered into similar structures for newbuildings 533, 534, and 535, respectively.<br />

The tax lease structures for newbuildings 532 and 533 are arranged by Banco Santander. The tax lease structure<br />

for newbuilding 534 is arranged by Banco Pastor. The tax lease structure for newbuilding 535 is arranged by<br />

Banco Popular. The tax lease structures are hereafter commonly referred to as the “Structure”. A brief overview<br />

of the Structure is provided below.<br />

<strong>Arrow</strong> has the following ships under construction as per agreements with the Spanish yard Factorias Vulcano<br />

S.A and their subsidiary Factorias Juliana S.A.U:<br />

Newbuild 532<br />

Contract price<br />

EUR 75.0 million<br />

Paid as of 31 December 2006 USD 18.2 million<br />

Agreed financing<br />

USD 56.8 million<br />

Contractual delivery February 2008<br />

<strong>Arrow</strong> will bareboat charter and after the expiry of the charter period own Newbuild 532 through the subsidiary<br />

ASI II.<br />

The book value as of 31 December 2006 is USD 18.2 million.<br />

Newbuild 533<br />

Contract price<br />

EUR 75.0 million<br />

Paid as of 31 December 2006 USD 10.4 million<br />

Agreed financing USD<br />

56.4 million<br />

Contractual delivery November 2008<br />

<strong>Arrow</strong> will bareboat charter and after the expiry of the charter period own Newbuild 533 through the subsidiary<br />

ASI III.<br />

The book value as of 31 December 2006 is USD 10.4 million.<br />

Newbuild 534<br />

Contract price<br />

EUR 76.3 million<br />

Paid as of 31 December 2006 USD 0<br />

Estimated financing<br />

USD 65 million<br />

Contractual delivery April 2009<br />

<strong>Arrow</strong> will bareboat charter and after the expiry of the charter period own Newbuild 534 through the subsidiary<br />

ASI V.<br />

92

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!