<strong>Environmental</strong> <strong>Management</strong> Plan <strong>Guideline</strong><br />
(iii)<br />
Small Project Issues-based Table<br />
<strong>Environmental</strong> <strong>Management</strong> Activities and Controls: Demolition Works – Noise<br />
Noise<br />
<strong>Environmental</strong> <strong>Management</strong> Control<br />
Ensure construction or demolition activities are restricted to <strong>the</strong><br />
following hours:<br />
- 7:00 am to 6:00 pm Monday to Friday<br />
- 8:00 am to 1:00 pm Saturday<br />
- No work on Sundays or public holidays<br />
If <strong>the</strong> hours <strong>of</strong> demolition and construction activities need to be<br />
varied, ensure prior written approval is obtained from <strong>the</strong> local<br />
council. Any request to alter construction hours should include:<br />
- a clear justification <strong>of</strong> <strong>the</strong> need <strong>for</strong> <strong>the</strong> work<br />
- details <strong>of</strong> <strong>the</strong> type <strong>of</strong> activity and <strong>the</strong> extended hours, and<br />
- an analysis <strong>of</strong> <strong>the</strong> resultant noise levels at residences in <strong>the</strong><br />
vicinity <strong>of</strong> <strong>the</strong> site.<br />
Be<strong>for</strong>e commencing work, send a letter to all residents and<br />
industrial/commercial users whose premises may be affected by<br />
demolition noise. Ensure <strong>the</strong> letter includes:<br />
- hours <strong>of</strong> operation and duration <strong>of</strong> <strong>the</strong> demolition work, and<br />
- contact details <strong>for</strong> more in<strong>for</strong>mation and/or to register<br />
complaints.<br />
Ensure that all noise complaints are recorded in a logbook.<br />
Ensure all complaints are investigated and concerns addressed.<br />
Ensure high efficiency mufflers are used on all construction<br />
equipment and manufacturer’s noise control equipment is intact.<br />
All equipment used on site shall have evidence <strong>of</strong> compliance with<br />
recommended noise levels outlined in AS2436, 1981.<br />
Person<br />
Responsible<br />
Timing / Frequency<br />
Completed<br />
(Initials/Date)<br />
Reference / Notes<br />
Site Supervisor During demolition SEE Section 4.11,<br />
Consent Condition 10<br />
Site Supervisor During demolition Consent Condition 11<br />
<strong>Environmental</strong><br />
Manager<br />
<strong>Environmental</strong><br />
Manager<br />
Site Supervisor<br />
Be<strong>for</strong>e demolition Consent Condition 12<br />
During demolition Consent Condition 13<br />
Be<strong>for</strong>e and during<br />
demolition<br />
SEE Section 4.11<br />
Ensure all construction equipment is well maintained. Site Supervisor During demolition SEE Section 4.11<br />