APPENDIX 9: REACTION FROM MININFRA TO THE COMMENTS FROM EU ON TRANSPORT<br />
LOGFRAME<br />
We should include in the Log Frame, under institutional strengthening, the formulation and<br />
implementation of a maintenance policy and prioritisation system. Actions will include data collection<br />
and creation of a prioritisation model (and a data base).<br />
The Classified road network includes National Roads, both paved and unpaved, and District roads<br />
which are either gravel or earth. The unclassified network is made up of rural feeder roads and tracks.<br />
The term Trunk Road should be replaced with National Road as it includes both paved and unpaved.<br />
The figures for the size of the road network are based on the DHV reclassification exercise and an<br />
estimation of the feeder road network at 8,500km. It is a priority of the Ministry to survey the feeder<br />
road network to establish accurate records of it’s size and condition.<br />
We should include in the Log Frame, under institutional strengthening, the formulation and<br />
implementation of a maintenance policy and prioritisation system.<br />
Lengths specified for Maintenance are cumulative as this is the only way to get correct cost figures as<br />
the unit cost (per km) is multiplied by the TOTAL length to give a total cost for the 5 years. This could<br />
be explained with a footnote.<br />
We need to check the figures for lengths of road to be maintained and rehabilitated included in the log<br />
frame as it’s unclear whether these should be for the baseline or unconstrained scenario.<br />
We do not have a baseline or any way of collecting data on Vehicle Operating Costs (VOC).<br />
Therefore this should be dropped from the Log Frame and we will rely on transport costs, for goods<br />
and passengers (container to Mombasa and a bus ticket to Kampala ).<br />
100 professional staff to be recruited will be in the district, approx 80, and in the Road Agency, approx<br />
20. They will all be responsible for planning and management of infrastructure development and<br />
maintenance contracts and supervision of works.<br />
Philippe needs to report on the reasons behind the formulation of the 2 nd generation FER.<br />
Philippe also needs to report on the reasons for Bugesara Airport.<br />
The establishment of Axle load control systems should be included as one of the activities under<br />
safety.<br />
The reduction in transport costs should be for a container to Mombasa and a bus ticket to<br />
Kampala and the reduction should be 10% rather than 30% which is too high.<br />
Richard and Amil will investigate the targets for maintenance and rehabilitation, whether they<br />
are for the baseline or unconstrained scenario and how achievable they are.<br />
The Akegera River scheme will include a feasibility study.<br />
Bridges have been included in road maintenance and rehabilitation and do not need a separate<br />
inclusion.<br />
Richard Smith<br />
Roads Expert<br />
MININFRA