24.10.2014 Views

Svetsaren 1/2008 - Esab

Svetsaren 1/2008 - Esab

Svetsaren 1/2008 - Esab

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Figure 8. FCAW of a lifting trunnion.<br />

Figure 9. SAW on a lifting trunnion.<br />

Foundation piles<br />

The foundation piles are pre-fabricated by Sif<br />

Group bv, arriving in 83-93 m lengths. To achieve<br />

their final length of 170 –190 m, they need to be<br />

welded together (Figure 10 and 11). This is again<br />

done by FCAW with PZ6138, but here it is<br />

mechanised welding with ESAB Railtrac equipment.<br />

The joint configuration is adapted to this<br />

method -an unsymmetrical X-joint with most of<br />

the weld volume on the outside. The inside part is<br />

welded manually, vertically-up. The root pass is<br />

deposited on ceramic backing. After removal of<br />

the fit-up plates, the majority of the weld volume<br />

is mechanised welded from the outside, verticallyup<br />

from 6 to 12 ‘o clock, mostly with a slight<br />

weaving motion. Welding parameters are adapted<br />

to the several clock positions by the operators.<br />

Dimensional control and weld finish<br />

Normal offshore fabrication, eg, a jacket on top of<br />

which the deck and operational facilities are placed,<br />

is naturally, subject to strict dimensions, but it is<br />

more forgiving than in the case of the Tombua<br />

Landana project. The fact is that three<br />

substructures, fabricated by three different yards,<br />

are stacked on top of each other in almost 400 m<br />

deep waters - and simply have to fit. This places<br />

extremely high demands on the dimensional control<br />

– roughly 3 times as high as normally required.<br />

This is as equally valid for the fabrication of the<br />

TBT’s components – the pile sleeve clusters and<br />

the rows – as it is for the assembly of the super<br />

structure. To exemplify the dimensional control<br />

and its implications for welding, we return to the<br />

fabrication of the pile sleeve clusters, shown in<br />

Figure 12.<br />

This image shows the completed pile sleeve cluster<br />

and the nominal distances between the centre<br />

lines of the pile sleeves and the centre line of the<br />

main leg (5172.5 and 5173 mm). The maximum<br />

acceptable tolerance on these distances is 3 mm.<br />

A similar small tolerance is valid on the distances<br />

between the pile sleeves themselves, in the X and<br />

Y directions and on the mutual distances into the<br />

Z direction. This dimensional control is the key<br />

requirement, and everything else is subject to it.<br />

Ideally, the pre-fabricated yoke plates, including<br />

K-bevel, fit exactly, so that there is a constant<br />

root gap between the pile sleeves/main leg and<br />

Figure 10. Welding tents made from shrink foil protect the weld area from wind and rain.<br />

the yoke plate’s K-bevel. In practice, this is<br />

extremely difficult to achieve. Practically always, the<br />

root gap appears to be more or less eccentric. This<br />

must be corrected by grinding on the narrow side<br />

and buttering & grinding on the wider side<br />

– an extremely time consuming exercise.<br />

Measuring was performed by three parties;<br />

Heerema Vlissingen, Passe-Partout (independent<br />

contractor) and Chevron, who worked<br />

independently according to agreed measuring<br />

principles. Chevron were responsible for final<br />

measuring and reporting.<br />

Another time-consuming aspect was Class C and<br />

Class A grinding of weld surfaces. Grinding is<br />

done with an aluminium oxide based disc.<br />

Class C grinding is required for the TKY joints<br />

between the braces and the dummy leg (middle<br />

of the row) and between the braces and the main<br />

leg of the pile sleeve cluster. It is performed to<br />

correct excessive convexity, notches or undercut<br />

at the toes of the weld. The grinding of the toes<br />

of the cap must be performed to the point where<br />

a 1 mm diameter wire cannot pass between the<br />

disc and the plate (Figure 13).<br />

Class A grinding is performed on the welds connecting<br />

the lower yoke plates to the main legs of<br />

the pile sleeve clusters – at both sides of the<br />

K-joint. Class A means that weld profile is ground<br />

back to the theoretical radius. This is checked by<br />

using a template with a 45 mm radius, with a gap<br />

12 - <strong>Svetsaren</strong> no. 1 - <strong>2008</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!