Mining segment, export sales, FCA based with discounts/price premium<br />

<strong>2007</strong> 2006 Change year-on-year %<br />

Thousand US$ Thousand US$ Thousand US$<br />

tonnes million tonnes million tonnes million<br />

Coking coal 81 3.1 40 2.0 102.5 55.0<br />

Coking coal concentrate 814 62.5 488 45.7 66.8 36.8<br />

Steam coal 601 15.0 429 17.0 40.1 (11.8)<br />

Pellets 2,187 124.7 3,285 211.0 (33.4) (40.9)<br />

Iron ore concentrate – – – – n.a. n.a.<br />

Scrap metal – 250.0 – 17.6 n.a. 1,320.5<br />

Total products – 455.3 – 293.3 n.a. 55.2<br />

Shipping and other – 99.5 – 16.3 n.a. 506.7<br />

Total export sales – 554.8 – 309.6 n.a. 79.2<br />

Inter-segment transactions – (53.2) – (92.1) n.a. n.a.<br />

Main coal production projects<br />

Development of the Vorkutaugol mine<br />

In this project, we are linking the four existing mines<br />

(Komsomolskaya, Severnaya, Vorkutinskaya, Zapolyarnaya)<br />

with a single trunk conveyer line, and providing the necessary<br />

infrastructure, both above and below ground, so we can increase<br />

lift productivity. We have currently suspended work on this project<br />

while we review and improve the safety measures. The aim of the<br />

project, ultimately, is to reduce our fixed costs.<br />

Development of the Vorgashorskaya mine<br />

With this project, we are aiming to increase extraction at the mine,<br />

to 4.0 million tonnes of steam coal a year (run of mine).<br />

Main projects for extracting and refining iron ore<br />

Development of the Korpangsky field<br />

The aim of this project is to open up new sections of the field. We<br />

plan to extract 83 million tonnes of ore. Of this, 40 million tonnes<br />

will come from the Severny-2 section and 43 million tonnes from<br />

the Zapadny section. We will have finished the project by 2013.<br />

Construction of the Olenegorsky underground mine<br />

The aim of this project is to support Olkon’s resource base so<br />

we can guarantee production of 5 million tonnes of iron ore<br />

concentrate a year. We started the project in 2003 and began<br />

extracting in 2004. We plan to reach our target capacity by 2009,<br />

and to have developed our reserves by 2024.<br />

Increasing the production capacity of the Karelsky Okatysh<br />

ore-dressing plant<br />

This project will increase the plant’s annual production of<br />

processed ore to 33 million tonnes. Production volumes of iron ore<br />

concentrate will amount to 11.7 million tonnes. We will improve<br />

productivity by modernising our equipment. The project began<br />

in 2006 and is due to be completed in 2009.<br />

Projects for 2008<br />

Geological exploration at the Tabornoye gold field<br />

We will be evaluating the possibility of expanding gold production<br />

and developing explored gold reserves. The project is estimated<br />

to cost US$74.8 million.<br />

Optimising the decontamination and methane utilisation<br />

system at Vorkutaugol<br />

We will be working with Steag Saar Energie to build vacuumpumping<br />

stations that will pump methane away from the mines<br />

and convert it into electricity. The project is estimated to cost<br />

US$156.8 million.<br />

Organising the process for flotation upgrading of metal<br />

content at Karelsky Okatysh<br />

We will be aiming to reduce alloy content and increase iron content.<br />

The project is estimated to cost US$24.7 million.<br />

<strong>Severstal</strong> <strong>Annual</strong> <strong>Report</strong> <strong>2007</strong> 39