All 34-m HEF<br />
except selective<br />
70-m from<br />
L+1789 to +1804d<br />
L+1733 to +1741d: 2*4 h/w<br />
L+1741 to +1747d: 2*8 h/w<br />
L+1747 to +1784d: 4 h/d<br />
L+1784 to +1789d: 8 h/d<br />
L+1789 to +1794d: 24 h/d<br />
L+1796 to +1799d: 24 h/d<br />
L+1799 to +1801d: 4 h/d<br />
L+1801 to +1804d: 24 h/d<br />
L+1804 to +1835d: 4 h/d<br />
L+1835 to +1841d: 2*4 h/w<br />
1. DSN Coverage should alternate between Northern Hemisphere and Southern Hemisphere DSN sites.<br />
2. A*B = A number of tracks at B frequency<br />
Table 6.3-2 OPNAV Plan<br />
Time<br />
Frequency<br />
no. of<br />
images<br />
bits /<br />
pixel<br />
no. of<br />
filters<br />
E -90 to -7 d 2 /wk 1 16 1<br />
(nav)<br />
E -7 to -2 d 1 per day same as above<br />
E -47 to -26 h 1 per hour same as above<br />
E -17 to -12h 1 per hour same as above<br />
Comments<br />
small yaw turn, mirror, pattern match<br />
and window.<br />
During the Post Encounter subphase, the primary objective is to transmit all of the data<br />
stored during the comet encounter. The spacecraft attitude for the first 19 days after<br />
encounter is planned to track the Earth with the HGA boresight to reduce spacecraft<br />
slewing. It is highly desirable to return this data as quickly as possible to prevent<br />
irretrievable loss in the event of a reboot of the spacecraft main computer. In addition,<br />
transmission of the data a total of three times is also desired to prevent loss of data due to<br />
communications problems. Approximately 55 hours are estimated to be required using<br />
HGA and 70-m capability (4000 bps) to return the stored data. With the HGA and 34-m<br />
capability (1000 bps), 220 hours are required to return the same data set. Tracking with<br />
70-m stations is requested to support three 55 hour periods with 1 day between each<br />
period to allow for spacecraft health and safety verification.<br />
82