The communications schedule only includes those communications events that require a<br />

slew. This results in no slews for some portions of launch (LGA comm: L+0-30 days),<br />

EGA (LGA comm: L+708-727 days), encounter (L+1789-1804 days), and return (LGA<br />

comm: L+2509-2535 days).<br />

10.2.3 Model Parameters and Characteristics<br />

The background attitude schedule, communications and OPNAV schedules used in the<br />

current modeling runs are summarized in Tables 10.2-5 through 10.2-7. The resultant ∆V<br />

magnitudes and directions are illustrated in Figures 10.2-2 through 10.2-4.<br />

dV magnitude (m/s)<br />

Declination (deg) [eme'2000]<br />

0.030<br />

0.025<br />

0.020<br />

0.015<br />

0.010<br />

0.005<br />

0.000<br />

40<br />

30<br />

20<br />

10<br />

0<br />

-10<br />

-20<br />

-30<br />

-40<br />

pitch/yaw/pitch<br />

5,6-8-1,2-5,6-8-5,6<br />

yaw/pitch<br />

(8,1,5,8)<br />

pitch/yaw combined<br />

(slews 3,7)<br />

pitch < 15°<br />

(slews 1,5)<br />

pitch > 15°<br />

(slews 2,6)<br />

d/b clamp<br />

(slew 4)<br />

mode<br />

comm<br />

opnav<br />

0 2 4 6 8 10 12 14 16 18 20 22 24 26<br />

Time (100 days from Launch)<br />

Figure 10.2-2 Slew ∆V Magnitude Profile<br />

dV<br />

ToSun<br />

ToEar<br />

all<br />

mode<br />

chgs<br />

one-way<br />

0 2 4 6 8 10 12 14 16 18 20 22 24 26<br />

Time (100 days from launch)<br />

Figure 10.2-3 Slew ∆V Direction Comparison - Declination<br />