Work Package<br />

Document: Work Package #1<br />

Project: Pen Project Author: Project Manager<br />

Date:<br />

1. Date<br />

2013-­‐06-­‐29<br />

2. Authorized body<br />

IT Department <br />

3. Description<br />

An evaluaDon form should be designed in a way that covers everything <br />

menDoned in the requirements document, yet simple enough for the <br />

evaluators to fill in. <br />

4. Techniques<br />

Since the data is to be collected in an spreadsheet later, the forms <br />

should be designed in a database friendly form. <br />

5. Interfaces<br />

If there are any quesDons about the requirements, the senior user <br />

would answer. <br />

5. Joint agreement<br />

A clear defini(on of the deliverable to be <br />

delivered by the team manager. <br />

The way we’re going to <br />

manage by excep(on. <br />

The project will not pay for internal resources, including the ones <br />

working on this work package. The original duraDon for this work <br />

package is two days; however, we are behind schedule and would be <br />

able to recover if it’s done earlier (less than one day) <br />

6. Tolerances<br />

Time: 0% | Cost: 0% | Scope: 0% |<br />

7. Constraints<br />

none The way they should report back to the <br />

Project Manager (in the form of <br />

8. Reporting arrangement Checkpoint Reports) <br />

All reports on this work package will be verbal and none-­‐official, at <br />

least twice a day. <br />

9. Problem handling and escalation<br />

Any problem which has an effect on the Dme should be immediately <br />

escalated to the project manager. <br />

10. Approval method<br />

The senior user will approve this form, based on how well it covers the <br />

factors stated in the requirements document. <br />

When the package will be accepted <br />

<strong>PRINCE2</strong>® is a Registered Trade Mark of the AXELOS. The Swirl logo is a Trade Mark of the AXELOS.<br />

© Management Plaza<br />

P2P-<strong>SampleProject</strong>-EN<br />

Version V01.14 – <strong>Premium</strong> Edition<br />

57

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!