Highlight Report<br />

Document: Highlight report # 4<br />

Project: Pen Project Author: Project Manager<br />

Date:<br />

1. Date and period of the report<br />

End of the second week of Stage 2, for a period of one week.<br />

2. Status summary<br />

TF: +5% | CF: ±0 | Project is going well so far. <br />

3. Work packages in this period<br />

• Selected supplier – completed <br />

• Catalogs of pens – completed (behind schedule) <br />

• Short list of pens to be evaluated – completed (behind schedule) <br />

• Purchase order of pens to be evaluated – not finished (behind <br />

schedule) <br />

• Sample pens for evaluaDon – not started (behind schedule) <br />

• Logo – completed <br />

I took two extra days for the supplier to send us the catalogs, and it <br />

made a delay in this and all successor work packages. <br />

5. Stage tolerances<br />

Time: TF = +5%, inside the tolerances set for the stage, and for the <br />

management level. <br />

Cost: CF = ±0% <br />

6. Change requests<br />

• We fell behind schedule because the supplier sent us catalogs two <br />

days later than we expected. We designed a correcDve acDon to get <br />

help from the IT department for two of our future work packages. <br />

We will recover Dme by this. (approved by project manager) <br />

7. Key issues and risks<br />

No excep(on yet. <br />

We might have more delays in receiving evaluaDon pens and the final <br />

pens from the supplier. <br />

4. Work packages for the next period<br />

• Purchase order of pens to be evaluated (moved from this period) <br />

• Sample pens for evaluaDon (moved from this period) <br />

• List of evaluators û <br />

• EvaluaDon form û <br />

• Next stage plan <br />

û We are going to get help from IT department to conduct these <br />

two packages faster and catch up on the planned schedule. <br />

<strong>PRINCE2</strong>® is a Registered Trade Mark of the AXELOS. The Swirl logo is a Trade Mark of the AXELOS.<br />

© Management Plaza<br />

P2P-<strong>SampleProject</strong>-EN<br />

Version V01.14 – <strong>Premium</strong> Edition<br />

65