<strong>Remeha</strong> <strong>Avanta</strong> <strong>Plus</strong><br />

• Open the boiler gas valve and check the static pressure to<br />

the boiler at the measurement point (C) on the gas block.<br />

C<br />

<br />

The boiler has been factory tested for natural gas at 20 mbar.<br />

The minimum gas inlet pressure is 17 mbar for natural gas<br />

(see 2.4.3).<br />

fi g. 36<br />

LT.AL.W7H.000.039<br />

Measurement point c on the gas block<br />

Check<br />

• Check that the gas supply to the boiler is gas tight (in<br />

compliance with the current regulations, see Chapter 7 the<br />

maximum test pressure at the gas pipe inlet, with the boiler<br />

gas valve open, is 60 mbar.<br />

• Vent the gas pipe by unscrewing the measurement point (C)<br />

on the gas block (tighten it again as soon as the pipe is fully<br />

vented).<br />

• Check that the gas connections in the boiler are sealed.<br />

• Check that all electrical connections, including the earth<br />

connection, have been made correctly.<br />

• Check the electrical connections to the thermostat and other<br />

external controls.<br />

• Check that the flue-gas and air-supply connections are<br />

sealed.<br />

3. Switching the boiler on and setting the controls<br />

• Replace the fuse in the spur and switch on the 230 V power<br />

supply.<br />

• Set the controls to heat demand.<br />

• The boiler will begin an automatic venting-programme<br />

(which lasts approx. 3 minutes) and will do this every time<br />

the power supply is isolated.<br />

• The boiler now starts to run. The operational status is shown<br />

in the display. The normal operating status finally shows 0<br />

in the display.<br />

fi g. 37<br />

112952.LT.GB.W7H.040<br />

Check electrical connections and thermostat<br />

4. Checking/setting the gas/air ratio at full load<br />

The <strong>Avanta</strong> <strong>Plus</strong> boilers are suitable for both natural gas and<br />

propane firing. An optional propane-set is needed (see par.<br />

2.4.2).<br />

The boilers are supplied as standard set for natural gas<br />

230 V<br />

(G20), therefore the following procedure must be carried out<br />

BEFORE the boilers are fired and commissioned for the first<br />

time on propane:<br />

- Fit propane set (instruction in kit);<br />

- adjust the fan speed (for procedure; see Par. 2.9.8, for values;<br />

see table 06 and table 08) and;<br />

- adjust the gas/air ratio (for values; see table 06 and table<br />

08).<br />

fi g. 38<br />

112952.LT.GB.W7H.041<br />

Power on and controls on heat demand<br />