Schedule 4 - Governance Model<br />
1. Relationship management and reporting overview<br />
A key critical success factor <strong>of</strong> the LMBR Program will be the realisation <strong>of</strong> a fully<br />
collaborative working approach and effective integration between DEC and the Contractor.<br />
Joint accountability will be assumed where possible, with the two parties working together to<br />
achieve a shared outcome.<br />
The approach to be taken must allow flexibility for change and be linked to the implementation<br />
<strong>of</strong> a program management framework that supports the management <strong>of</strong> such change. For<br />
guidance regarding the LMBR Program management and governance frameworks please<br />
reference, Part B, Section 2.3.4 and Part C, Section 8 <strong>of</strong> the RFP.<br />
The approach to be taken must also evidence understanding <strong>of</strong> the complex DEC stakeholder<br />
landscape and the diversity <strong>of</strong> environments within which those stakeholders operate. For<br />
further detail regarding envisaged impacts on stakeholders and those business engagement<br />
mechanisms that are currently in place please reference, Part B, Section 2.3.6 <strong>of</strong> the RFP.<br />
DEC believes a successful Contractor relationship is based on several key tenets:<br />
(a)<br />
(b)<br />
(c)<br />
(d)<br />
(e)<br />
(f)<br />
(g)<br />
(h)<br />
collaborative working;<br />
high value to DEC;<br />
adequate return for the Contractor;<br />
mutual trust and respect;<br />
good faith;<br />
good cultural fit;<br />
understanding <strong>of</strong> differing contexts and environments across DEC; and<br />
open and honest communication between both parties.<br />
2. Operating principles<br />
The following operating principles provide a uniting vision in support <strong>of</strong> the joint achievement<br />
<strong>of</strong> common goals. DEC will work collaboratively with the Contractor to:<br />
(a)<br />
(b)<br />
(c)<br />
(d)<br />
ensure adoption <strong>of</strong> a value led approach;<br />
ensure excellence <strong>of</strong> service provision to end users;<br />
ensure readiness and maturity <strong>of</strong> the organisation to adapt to change; and<br />
ensure clear identification and delineation <strong>of</strong> roles and responsibilities, which will<br />
be agreed as part <strong>of</strong> this agreement.<br />