India's largest coal handling agency - Mjunction
India's largest coal handling agency - Mjunction
India's largest coal handling agency - Mjunction
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Expert Speak<br />
Internal lining work of bridge pipe is in progress in coke oven plant<br />
bricks started coming out one by one and the castable, which<br />
took support from these bricks, collapsed gradually, thereby<br />
exposing the ceramic fibre board layers as well as the lower<br />
metallic edge of the cast iron door to direct heat. The lower<br />
edge and some portion of the exposed rib started melting<br />
down. The molten iron falling on the lower doors started<br />
damaging them in turn.<br />
2) Lower Oven Doors<br />
The damage and melting down of the upper oven doors<br />
spread extensively to the lower oven doors also. The molten<br />
iron falling on the refractory lining of the lower oven door first<br />
damaged the refractory, which gave way, thereby exposing<br />
the lower door metal to direct heat. The ribs of the lower<br />
door melted down. Thus, a large number of lower doors also<br />
got heavily damaged and became unserviceable. The first<br />
replacement activity of Lower Oven Doors was started in<br />
March 2008.<br />
free space below the arch roof and the rest of the unburned<br />
gas, along with the hot burnt flue gas, travels down to the<br />
sole flue which is divided into four linked arches below the<br />
oven sole. Additional combustion air known as secondary<br />
air is introduced in the sole flue to complete the balance 20<br />
percent combustion and the hot inert flue gas, devoid of any<br />
combustible constituent, is allowed to go up the uptakes to the<br />
bridge pipes, the branch header and finally to the chimney via<br />
the waste heat boiler, for recovery of waste heat from the hot<br />
flue gases for generation of power.<br />
The damage of bridge pipes commenced from the early<br />
days of commissioning. The commissioning of battery nos.7<br />
and 8 started towards end of December 2007. Thereafter,<br />
sequentially other batteries were commissioned in January<br />
2008(nos. 5 and 6), March 2008 (nos. 3 and 4) and May 2008<br />
(nos.1 and 2). The damage of bridge pipes started in the<br />
months of January to February 2008 and the first replacement<br />
was done in Oven no. 86 coke side (Battery no. 8) on February<br />
13, 2008. It meant that the damage of the bridge pipe had<br />
commenced within a month’s time of the first commissioning.<br />
During subsequent months, replacement of damaged bridge<br />
pipes went on as follows: March 2008-3 nos., April 2008-<br />
3 nos., May 2008-6 nos., June 2008-7 nos., July 2008-8 nos.,<br />
August 2008-5 nos., September 2008-5 nos., Oct 2008-7 nos.,<br />
November 2008-6 nos., December 2008-10 nos., and so on.<br />
Translated year–wise, the bridge pipe replacements were as<br />
follows: 2008-61 nos., 2009-147 nos. and 2010 (till July)-66 nos.<br />
There was a time when bridge pipes got damaged within a<br />
few days of installation.<br />
Observations and Remedial Actions<br />
Upper Oven Doors<br />
The first action with regard to the upper oven doors was to<br />
make some changes in the design of the liner. The L-shaped<br />
bricks were replaced with dense castable LC-45, cast on<br />
L-shaped ss-anchorage. Ceramic Fibre castable of the main<br />
3) Bridge Pipes<br />
Bridge Pipes are breather pipes for ovens and serve as nostrils<br />
for the oven chambers. Each oven, therefore, has two bridge<br />
pipes connected to two separate branch headers – one at the<br />
pusher side and the other at the coke side. These create the<br />
necessary suction inside the oven uniformly from both ends<br />
for inhaling combustion air into the free space above the <strong>coal</strong><br />
cake. The inhaled air helps in burning of volatile substances<br />
ejected out of the <strong>coal</strong> cake and creates a fire ball which<br />
radiates heat in all directions. The arched oven roof serves as<br />
a concave mirror and reflects the radiations in parallel vertical<br />
rays falling on the <strong>coal</strong> cake.<br />
The entry of air into the oven should be so controlled that<br />
80 percent of the combustion is completed in the oven top<br />
Chart showing gradual decline of damaged upper doors vis-à-vis<br />
increasing nos. in good condition<br />
COAL INSIGHTS 56 October 2010