21.01.2015 Views

India's largest coal handling agency - Mjunction

India's largest coal handling agency - Mjunction

India's largest coal handling agency - Mjunction

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Expert Speak<br />

Internal lining work of bridge pipe is in progress in coke oven plant<br />

bricks started coming out one by one and the castable, which<br />

took support from these bricks, collapsed gradually, thereby<br />

exposing the ceramic fibre board layers as well as the lower<br />

metallic edge of the cast iron door to direct heat. The lower<br />

edge and some portion of the exposed rib started melting<br />

down. The molten iron falling on the lower doors started<br />

damaging them in turn.<br />

2) Lower Oven Doors<br />

The damage and melting down of the upper oven doors<br />

spread extensively to the lower oven doors also. The molten<br />

iron falling on the refractory lining of the lower oven door first<br />

damaged the refractory, which gave way, thereby exposing<br />

the lower door metal to direct heat. The ribs of the lower<br />

door melted down. Thus, a large number of lower doors also<br />

got heavily damaged and became unserviceable. The first<br />

replacement activity of Lower Oven Doors was started in<br />

March 2008.<br />

free space below the arch roof and the rest of the unburned<br />

gas, along with the hot burnt flue gas, travels down to the<br />

sole flue which is divided into four linked arches below the<br />

oven sole. Additional combustion air known as secondary<br />

air is introduced in the sole flue to complete the balance 20<br />

percent combustion and the hot inert flue gas, devoid of any<br />

combustible constituent, is allowed to go up the uptakes to the<br />

bridge pipes, the branch header and finally to the chimney via<br />

the waste heat boiler, for recovery of waste heat from the hot<br />

flue gases for generation of power.<br />

The damage of bridge pipes commenced from the early<br />

days of commissioning. The commissioning of battery nos.7<br />

and 8 started towards end of December 2007. Thereafter,<br />

sequentially other batteries were commissioned in January<br />

2008(nos. 5 and 6), March 2008 (nos. 3 and 4) and May 2008<br />

(nos.1 and 2). The damage of bridge pipes started in the<br />

months of January to February 2008 and the first replacement<br />

was done in Oven no. 86 coke side (Battery no. 8) on February<br />

13, 2008. It meant that the damage of the bridge pipe had<br />

commenced within a month’s time of the first commissioning.<br />

During subsequent months, replacement of damaged bridge<br />

pipes went on as follows: March 2008-3 nos., April 2008-<br />

3 nos., May 2008-6 nos., June 2008-7 nos., July 2008-8 nos.,<br />

August 2008-5 nos., September 2008-5 nos., Oct 2008-7 nos.,<br />

November 2008-6 nos., December 2008-10 nos., and so on.<br />

Translated year–wise, the bridge pipe replacements were as<br />

follows: 2008-61 nos., 2009-147 nos. and 2010 (till July)-66 nos.<br />

There was a time when bridge pipes got damaged within a<br />

few days of installation.<br />

Observations and Remedial Actions<br />

Upper Oven Doors<br />

The first action with regard to the upper oven doors was to<br />

make some changes in the design of the liner. The L-shaped<br />

bricks were replaced with dense castable LC-45, cast on<br />

L-shaped ss-anchorage. Ceramic Fibre castable of the main<br />

3) Bridge Pipes<br />

Bridge Pipes are breather pipes for ovens and serve as nostrils<br />

for the oven chambers. Each oven, therefore, has two bridge<br />

pipes connected to two separate branch headers – one at the<br />

pusher side and the other at the coke side. These create the<br />

necessary suction inside the oven uniformly from both ends<br />

for inhaling combustion air into the free space above the <strong>coal</strong><br />

cake. The inhaled air helps in burning of volatile substances<br />

ejected out of the <strong>coal</strong> cake and creates a fire ball which<br />

radiates heat in all directions. The arched oven roof serves as<br />

a concave mirror and reflects the radiations in parallel vertical<br />

rays falling on the <strong>coal</strong> cake.<br />

The entry of air into the oven should be so controlled that<br />

80 percent of the combustion is completed in the oven top<br />

Chart showing gradual decline of damaged upper doors vis-à-vis<br />

increasing nos. in good condition<br />

COAL INSIGHTS 56 October 2010

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!