14.2 Airport Development <strong>Plan</strong>s - Indicative Program<br />

The following tables outline the indicative implementation plans for the key development plans described in this Draft <strong>Master</strong> <strong>Plan</strong> <strong>2009</strong>. It<br />

must be stressed that these timeframes are only indicative and specific elements may be brought forward or delayed.<br />

A number of the projects in the following tables will require the development of an Major Development <strong>Plan</strong> (MDP). Those<br />

projects that are likely to trigger an MDP are indicated with an asterisks.<br />

Short Term (<strong>2009</strong>-2014)<br />

Development Project<br />

*Terminal WA and<br />

Associated Ground Transport<br />

Airfield Taxiway Improvements<br />

International Terminal<br />

Arrivals Extension<br />

International Terminal Departure<br />

Concourse Extension and Aerobridges<br />

Inter Precinct Road<br />

Domestic Terminals<br />

Forecourt Upgrade<br />

Additional Car Parking<br />

Consolidated Precinct<br />

Ground Transport<br />

Terminal 3 Expansion<br />

Commercial Developments<br />

Description<br />

Construction of a single storey terminal building of approximately 19,000 square metres<br />

together with associated ground transport facilities and road access.<br />

Construction of additional taxiway connections to provide capacity for aircraft from the<br />

new apron for Terminal WA.<br />

Provision of additional baggage reclaim facilities and extension to the border agencies<br />

process area.<br />

Construction of additional departure lounge space and a new concourse with<br />

aerobridge served positions on each side.<br />

The construction of an on airport public road linking the new roundabout in Brearley<br />

Avenue on the domestic side travelling around the southern end of the main runway<br />

and connecting to Horrie Miller Drive.<br />

This project involves the improvement of flow and capacity on the forecourt together<br />

with modifications to traffic flow to split modes of transport on the approach and exit to<br />

the forecourt.<br />

Car parking is required for staff, short-term and long-term users. These facilities will initially<br />

be developed at grade and as capacity grows multi-storey facilities will be constructed with<br />

the first one being located nearest to the ultimate Consolidated Terminal.<br />

Construction of road access to the reconfigured forecourt in the Consolidated Precinct.<br />

Key features include separation of vehicles from the face of the terminal and separation<br />

of pedestrian traffic from vehicle traffic.<br />

Extensions to the departure hall and the provision of additional aerobridge positions to<br />

cater for growth until consolidation.<br />

Predominantly for existing tenant expansion in the initial stages and then in areas<br />

conducive to the market of the day.<br />

* MDP likely to be required<br />