<strong>Steam</strong> <strong>Generator</strong> & Fluid Heater<br />
<strong>Installation</strong> <strong>Manual</strong><br />
IMPORTANT<br />
KEEP CLAYTON EQUIPMENT CLEAR OF ALL OBSTRUCTIONS. DO NOT ROUTE<br />
ANY NON-CLAYTON PIPING, ELECTRICAL CONDUIT, WIRING, OR APPARATUS<br />
INTO, THROUGH, OR UNDER CLAYTON EQUIPMENT. ANY OBSTRUCTIONS<br />
CREATED BY SUCH NON-CLAYTON APPARATUS WILL VERY LIKELY INTER-<br />
FERE WITH THE PROPER OPERATION AND SERVICING OF THE EQUIPMENT.<br />
ALL SUCH INTERFERENCE IS THE SOLE RESPOSIBILITY OF THE CUSTOMER.<br />
CLAYTON’S PLAN INSTALLATION DRAWINGS, INCLUDING JOB-SPECIFIC<br />
DRAWINGS, ARE FOR VISUAL REFERENCE ONLY.<br />
2.2 Positioning and Anchoring Equipment<br />
2.2.1 General <strong>Installation</strong> Requirements<br />
Lifting instructions are provided in Appendix A. Proper rigging practices and equipment must be<br />
applied when lifting this equipment. Forklifts with roll bars can be used for installations with overhead space<br />
limitations.<br />
WARNING<br />
DO NOT attach rigging gear to the top coil lifting hook or any part of this equipment<br />
other than the main frame.<br />
When used, mounting legs with fasteners are provided. All legs and fasteners must be attached.<br />
DO NOT alter the lengths of the mounting legs without first consulting <strong>Clayton</strong>. The mounting legs are<br />
designed to provide adequate space and accessibility for servicing the equipment. Proper floor drains must<br />
be provided under the generator(s). MAKE SURE ALL EQUIPMENT IS LEVELED AND ALL<br />
ANCHORING POINTS ARE USED.<br />
Level the equipment using full-size, stainless steel, slotted shims that match the equipment<br />
pads designed and provided on the equipment. <strong>Clayton</strong> recommends full-size slotted shims. If slotted<br />
machine shims are used, <strong>Clayton</strong> requires C-size or larger for pump skids and E-size for generator<br />
and water skids. Use full-sized anchors to anchor the equipment. Make sure anchors are strong<br />
enough to withstand operating, wind, and seismic loads that exists in the installation location.<br />
To enhance serviceability and accommodate service personnel, <strong>Clayton</strong> recommends placing its generators,<br />
main positive displacement (PD) feedwater pumps, feedwater skids, and water treatment skids on 4–<br />
6 inch (10–15 cm) high equipment maintenance pads. These equipment maintenance pads on which the<br />
equipment will be installed must be 3–6 inches (8–15 cm) wider and longer than the equipment base plates.<br />
Make sure the equipment maintenance pads are properly reinforced and leveled.<br />
Fully grout into place all generators, pumps, and skids, after leveling and anchoring, to provide adequate<br />
support and minimize equipment vibration. Grouting is important, but it does not replace the use<br />
of metal shims under each anchor bolt location. Every anchor hole location on the equipment skid(s)<br />
requires an anchor bolt.<br />
Sect02_Genrl-xx4_s.fm 2-2 04/21/2015