3.6 SEMI-CLOSED RECEIVER (SCR)<br />
Semi-closed receiver systems are used only in applications that return a large amount (typically<br />
> 50%) of high pressure, high temperature, condensate. The SCR is a pressurized vessel<br />
that is maintained at a pressure that will minimize venting (wasting) of the excess system heat<br />
contained in the hot condensate returns. Feedwater outlet line sizing is critical. See Section 2.11.<br />
Each semi-closed receiver system is unique and requires individual attention to ensure<br />
proper application, installation and operation.<br />
Due to the nature and selected use of semi-closed receiver systems, they are addressed in<br />
supplemental instructions.<br />
3.7 SEMI-CLOSED RECEIVER SKIDS<br />
These skids must be shipped with the SCR tank loose. Tank and interconnecting piping<br />
must be assembled by the installer.<br />
3.8 HEAD TANK<br />
A 10-gallon head tank is required when proper receiver tank elevation is unavailable. A<br />
head tank provides the necessary positive coil feed pressure during wet layup. The tank must be<br />
installed at least two (2) feet above the steam generator coil inlet connection.<br />
Sect03_FeedwtrSys_xx4_f.fm 3-8 04/22/2015