STEAM GENERATOR & FLUID HEATER<br />

INSTALLATION MANUAL<br />

3.6 SEMI-CLOSED RECEIVER (SCR)<br />

Semi-closed receiver systems are used only in applications that return a large amount (typically<br />

> 50%) of high pressure, high temperature, condensate. The SCR is a pressurized vessel<br />

that is maintained at a pressure that will minimize venting (wasting) of the excess system heat<br />

contained in the hot condensate returns. Feedwater outlet line sizing is critical. See Section 2.11.<br />

Each semi-closed receiver system is unique and requires individual attention to ensure<br />

proper application, installation and operation.<br />

Due to the nature and selected use of semi-closed receiver systems, they are addressed in<br />

supplemental instructions.<br />

3.7 SEMI-CLOSED RECEIVER SKIDS<br />

These skids must be shipped with the SCR tank loose. Tank and interconnecting piping<br />

must be assembled by the installer.<br />

3.8 HEAD TANK<br />

A 10-gallon head tank is required when proper receiver tank elevation is unavailable. A<br />

head tank provides the necessary positive coil feed pressure during wet layup. The tank must be<br />

installed at least two (2) feet above the steam generator coil inlet connection.<br />