NOTE<br />

It is imperative that proper feedwater treatment chemicals and equipment are in<br />

place and operational prior to filling the heating coil.<br />

The <strong>Clayton</strong> Feedwater Treatment <strong>Manual</strong>, furnished with each new unit, provides detailed information<br />

regarding <strong>Clayton</strong> feedwater treatment requirements, products, and equipment.<br />

In general, the feedwater supplied to your <strong>Clayton</strong> steam generator must:<br />

• Hardness: 0 ppm (4 ppm maximum)<br />

• pH 10.5–11.5 (normal range), maximum of 12.5<br />

• Oxygen free with an excess sulfite residual of 50–100 ppm during operation (>100 ppm during<br />

wet lay-up)<br />

• Maximum TDS of 8,550 ppm (normal range 3,000–6,000 ppm)<br />

• Maximum dissolved iron of 5 ppm<br />

• Free of suspended solids<br />

• Maximum silica of 120 ppm with the proper OH alkalinity<br />

NOTE<br />

Review the <strong>Clayton</strong> <strong>Industries</strong> Feedwater Treatment Reference <strong>Manual</strong> (P/N:<br />

R15216) for additional feedwater quality requirements, or contact your local <strong>Clayton</strong><br />

Chemical Sales Representative.<br />

2.7.1 Water Softeners<br />

Refer to the <strong>Clayton</strong> Water Softener Instruction <strong>Manual</strong> for detailed information regarding the installation,<br />

dimensions, and operation of <strong>Clayton</strong> water softening equipment. Some general guidelines are provided<br />

below.<br />

Cold water piping to the water softener(s), and from the water softeners to the makeup water control<br />

valve should be Schedule 40 galvanized steel or Schedule 80 PVC.<br />

Install anti-siphon device (if required by local health regulations) in the raw water supply line.<br />

2.7.2 Make-up Water Line Sizing<br />

Table 2-3 shows the pipe sizes required from the water softener to hot-well. The supply pressure<br />

must be at least 65 psi (450 kPa).<br />