11.07.2015 Views

F4E Annual Report 2010 - Fusion For Energy - Europa

F4E Annual Report 2010 - Fusion For Energy - Europa

F4E Annual Report 2010 - Fusion For Energy - Europa

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Site, Buildings and Power Supplies• Site infrastructure and all the concrete and steelframe buildings (454.17 kIUA);• Power Supplies - pulsed power & steady statepower supplies (31 kIUA).Other Systems• Waste Management and Storage (10.1 kIUA);• Radiological Protection (4.2 kIUA).An important activity of <strong>F4E</strong> concerns the Test BlanketModules (TBMs) which are components that wouldallow the breeding of tritium in a fusion reactor. TheTBMs are not among the items which are obliged tobe provided by Europe to the ITER IO. Instead theTBMs are to be procured separately by the interestedParties and installed in ITER whereupon a TBM testingprogramme will be conducted by ITER.In carrying out its tasks, <strong>F4E</strong> also carries out a numberof Technical Support Activities which support theabove-mentioned activities and cover the followingareas:••Plasma Engineering;••Safety and Licensing;••Leak Detection & Leak Localisation;••Engineering Support;••Nuclear Data;••Quality Assurance Activities.In some cases the necessary technologies are wellestablished, but in many others R&D and designactivities are required before a document, known asa Procurement Arrangement (PA), setting out scopeof the procurement can be signed between ITER and<strong>F4E</strong>.<strong>For</strong> activities prior to procurement, <strong>F4E</strong> providessupport to the ITER IO through so-called TaskAgreements and R&D activities are typically carriedout in collaboration with European national fusionlaboratories under the cost-sharing arrangementprovided for by grants.<strong>F4E</strong> is also carrying out detailed risk assessmentsto identify any unresolved problems and risks withthe design, manufacturing and assembly and torecommend actions to mitigate the risks. This may becomplemented by Design Reviews carried out jointlywith the ITER IO.HighlightsOne of the highlights of <strong>2010</strong> was the approvalby the ITER Council in July <strong>2010</strong> of the updatedITER Baseline (scope, schedule and cost) for ITERoperation in November 2019. <strong>F4E</strong> devoted significantinternal resources to the development of this updatedBaseline under the guidance of the <strong>F4E</strong> GoverningBoard (GB).Overall the activities of <strong>F4E</strong> conducted during <strong>2010</strong>were according to the schedule defined in theupdated ITER Baseline (Fig. 2). In cases where therewere delays, these were either mitigated or did notadversely impact upon the critical path for ITERconstruction (i.e. no delay in the target date to beginITER operations).As concerns the <strong>2010</strong> Work Programme (WP <strong>2010</strong>),the pie-chart in Fig. 3 below shows the situation atthe end of the year whereby 54% of the foreseenprocurement procedures were started or completedand a further 41% were under preparation (withearmarked “global” financial commitments) and only5% cancelled.Overall the activities of <strong>F4E</strong> conducted during <strong>2010</strong>were consistent with the updated ITER Baseline. Incases where there were delays, these were eithermitigated or did not adversely impact upon the criticalpath for ITER construction (i.e. no influence on theNovember 2019 target to begin ITER operations).In <strong>2010</strong> <strong>F4E</strong> made important progress for in-kindprocurements of components on the critical path forITER construction by signing the contracts for themanufacturing of both the Toroidal Field coil WindingPacks and the Vacuum Vessel sectors, the latter beingthe largest contract awarded by <strong>F4E</strong> to date.In total 44 contracts and 23 grants were awardedby <strong>F4E</strong> for values of EUR 826 and EUR 8 millionrespectively (see Annex II). All but one of the foreseenProcurement Arrangements with a value of 384.44kIUA (equivalent to EUR 615 million) were signed withITER IO bringing the total to 803.74 kIUA (Fig. 4).In summer <strong>2010</strong>, following the completion of the siteclearance and levelling, ITER IO handed over the ITERplatform to <strong>F4E</strong>. The excavations were started andconstruction of the Poloidal Field coils fabricationbuilding began. At the same time the architectengineer started its work in <strong>2010</strong> to prepare forplacing the construction contracts for the civil worksand buildings.A special effort was devoted to improve the overall<strong>F4E</strong> project management processes, in line withthe proposals of the <strong>F4E</strong> Director approved by theGoverning Board. Risk assessments were also carriedout together with the identification of cost reductionsand cost containment opportunities to be applied toall <strong>F4E</strong> activities.ANNUAL REPORT <strong>2010</strong> FUSION FOR ENERGY23

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!