12.07.2015 Views

Draft Overview of HPC Construction - EDF Hinkley Point

Draft Overview of HPC Construction - EDF Hinkley Point

Draft Overview of HPC Construction - EDF Hinkley Point

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Dewatering <strong>of</strong> the working areas around the areas proposed for deeperexcavations during the main construction phase. Water collected from dewateringwould be discharged to the surface water drainage system described above. <strong>Construction</strong> <strong>of</strong> a temporary retaining structure along part <strong>of</strong> the northern edge <strong>of</strong>the main platform to retain the elevated main platform above the natural gradelevel. Development <strong>of</strong> a network <strong>of</strong> haulage roads to facilitate the movement <strong>of</strong> vehiclesand soil and rock materials around the site, including: a north-south haulage road which would allow for the transfer <strong>of</strong> excavatedmaterial to the southern part <strong>of</strong> the site; a haulage road network in the northern part <strong>of</strong> the site, which would vary inlocation and level to suit the ongoing platform development to eventually tieinto the site compounds as they are developed; and a service road around the perimeter <strong>of</strong> the site within the security fence toallow security and maintenance personnel access to inspect and maintain thefence line. <strong>Construction</strong> <strong>of</strong> site access points to the north-east <strong>of</strong> the site to provide the mainsite access during the site preparation works, with a second site access gate tothe south-east <strong>of</strong> the site to provide access for Heavy Goods Vehicles (HGVs)and deliveries to the site. Two roundabouts would be constructed to the north-eastand south-east <strong>of</strong> the site to serve these access points. Installation and commissioning <strong>of</strong> two batching plants; these will not be used forconcrete production with the exception <strong>of</strong> concrete tests until the DevelopmentConsent is granted.b) Temporary Jetty3.3.3 The applications for the temporary jetty provided for the construction and operation <strong>of</strong>a temporary jetty extending <strong>of</strong>f the north-west coast <strong>of</strong> the construction site including: <strong>Construction</strong> <strong>of</strong> haulage roads, including access to and along the beach t<strong>of</strong>acilitate construction <strong>of</strong> the onshore works; Piling for the jetty bridge and head, using tubular steel piles. The piles will beinserted using either the ‘drill and drive’ technique or into pre-drilled socketswhere they would be grouted into place. The onshore and foreshore piles wouldbe inserted using land-based equipment. The <strong>of</strong>fshore piling would use a jack-upbarge; <strong>Construction</strong> <strong>of</strong> the jetty bridge, incorporating a roadway and conveyors foraggregate and cement; <strong>Construction</strong> <strong>of</strong> the jetty head, incorporating ship mooring provisions, aggregateand cement receipt equipment and facilities for jetty workers;DRAFT | <strong>Overview</strong> <strong>of</strong> <strong>HPC</strong> <strong>Construction</strong> | February 2011 13

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!