CAPX<strong>20</strong><strong>20</strong>Group 1 ProjectsNearly 700 miles and $1.7 billion• Upsizing adds about $<strong>20</strong>0 millionFargo-St. Cloud-MonticelloBrookings County-HamptonHampton-Rochester-La CrosseBemidji-Grand Rapids250-miles, 345-kV240-miles, 345-kV150-miles, 345-kV70-miles, 230-kV• Alleviates emerging community servicereliability concerns around the state• Critical foundation for future transmission andgeneration• Provide needed transmission capacity tosupport new generation outlet• In-service dates from <strong>20</strong>11-<strong>20</strong>15• CAPX <strong>20</strong><strong>20</strong> Group 1 projects resulted from Vision plan