12.07.2015 Views

NSP System: 10-Year Transmission Plan / 20-Year ... - Xcel Energy

NSP System: 10-Year Transmission Plan / 20-Year ... - Xcel Energy

NSP System: 10-Year Transmission Plan / 20-Year ... - Xcel Energy

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Sioux Falls Area• Largest loads served by 115kV lines in the area:• West Sioux Falls• Cherry Creek substations• Peak load shed required forseveral transmissioncontingencies to meet NERCTPL-003 standard• Distribution need for a newsubstation in the city toaccommodate load growthbeyond the capabilities of 69kV• Rebuild <strong>10</strong> miles of 69 kV to115 kV, including 6 miles ofdouble circuit 115/69 kV• Sioux Falls substation will berelocated to accommodatethe larger lines anddistribution needs

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!