NSP System: 10-Year Transmission Plan / 20-Year ... - Xcel Energy
NSP System: 10-Year Transmission Plan / 20-Year ... - Xcel Energy
NSP System: 10-Year Transmission Plan / 20-Year ... - Xcel Energy
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Proposed <strong>Transmission</strong> ProjectsZone 5: Northern Wisconsin Area (<strong>20</strong>15-<strong>20</strong>19)# Project Comments Drivers1 BayfieldLoop 115 kV2 Pokegama161/69kVSubstation3 Withee115/69 kVTransformerRebuild existing Iron River –Gingles 34.5 kV loop to 115 kVwith some DistributionunderbuildBuild a new 161/69kV substationat Pokegama and build a linefrom BarronInstall a 1<strong>20</strong> MVA transformer atWitheeLoadShedReliabilityReliabilityNote: Project scope and timing subject to change