10<br />
Performance (cont.)<br />
Ausgrid met average reliability standards<br />
in each feeder category in 2014/15. During<br />
this period, 61 distribution feeders exceeded<br />
their feeder category thresholds and<br />
required investigation. All actions required<br />
as a result of these investigations were met<br />
in the relevant timeframes.<br />
A number of targeted projects were<br />
completed during the year to improve<br />
reliability for identified customers.<br />
These projects had a total value of<br />
$2.3 million and included the installation<br />
of seven reclosers and 13 remote<br />
controlled switches. The reclosers and<br />
control switches reduce the number of<br />
customers experiencing sustained outages<br />
and shorten the time taken to locate<br />
network faults. Ausgrid also replaced<br />
bare overhead conductors with covered<br />
conductors in some heavily vegetated areas<br />
to reduce the number of interruptions<br />
caused by trees and other vegetation.<br />
Improving customer service<br />
In 2014/15, we focussed on enhancing<br />
our customers’ experience. These efforts<br />
were supported by a new Customer<br />
Commitment Statement introduced in<br />
April 2015, outlining what customers<br />
could expect from the organisation.<br />
Ausgrid's Customer Satisfaction Index result<br />
for 2014/15 was 78.7 percent, lower than<br />
the target of 80 percent but an improvement<br />
of 1.3 percent on the 2013/14 result.<br />
Other opportunities to enhance Ausgrid’s<br />
customer service were identified, including<br />
partnering with retailers to provide<br />
better outcomes for customers. A range<br />
of self‐service reporting forms were also<br />
implemented on Ausgrid’s website and<br />
mobile website.<br />
Throughout the year, Ausgrid had seven<br />
immediately reportable breaches of the<br />
National Energy Customer Framework<br />
(NECF), where we failed to provide the<br />
required advance notice to registered life<br />
support customers about planned power<br />
outages. The importance of notifying<br />
registered life support customers is<br />
recognised and letters were sent to about<br />
20,000 of these vulnerable households<br />
in mid‐2015, providing information and<br />
contact details.<br />
Deliver the network plan<br />
Network investment<br />
Ausgrid is committed to delivering a safe,<br />
reliable and affordable electricity supply.<br />
Under reforms commenced by the NSW<br />
Government in 2012, we are working<br />
to make the network more efficient<br />
and reduce expenditure to help put<br />
downward pressure on consumer prices.<br />
In 2014/15 Ausgrid invested $579 million in<br />
our electricity network – almost 45 percent<br />
less than the approved capital expenditure<br />
of $1,008 million. This reduction was the<br />
result of significant changes to investment<br />
governance. This investment included a focus<br />
on lower cost delivery models, and a review<br />
of approval conditions which led to a number<br />
of projects being cancelled and/or deferred.<br />
The expected continuing decline in electricity<br />
consumption has allowed risk factors for<br />
current asset conditions to be reassessed.<br />
Capital investment during 2014/15 included<br />
$211 million for major substation and feeder<br />
projects, including new substations brought<br />
into service at Rose Bay and Waverley.<br />
Major refurbishments were completed<br />
at St Peters and Bunnerong North, along<br />
with sub‐transmission feeder projects at<br />
North Sydney, Belmore Park and Engadine.<br />
More than 543 kilometres of high and low<br />
voltage cables were commissioned during<br />
2014/15 and work continued on 67 major<br />
projects, including new sub‐transmission<br />
feeders from Mason Park to Rozelle, Lindfield<br />
to Willoughby, and Lindfield to Castle Cove,<br />
and zone substations at Olympic Park,<br />
Engadine, Metford and Tighes Hill.<br />
Detailed design and development<br />
commenced on seven major projects<br />
and construction was approved<br />
for seven substation upgrades and<br />
sub‐transmission feeder projects, including<br />
new sub‐transmission substations<br />
at Munmorah and Alexandria.<br />
In addition to this capital expenditure,<br />
390,809 planned maintenance tasks<br />
and checks were completed across the<br />
network, involving operational expenditure<br />
of more than $295 million. This includes<br />
underground and overhead line inspections,<br />
pole inspections and treatments, bushfire<br />
patrols and substation inspections.<br />
System average interruption<br />
frequency index (SAIFI)<br />
10/11<br />
10/11<br />
11/12<br />
13/14<br />
1.09<br />
11/12<br />
13/14<br />
14/15<br />
98*<br />
14/15<br />
12/13<br />
0.82<br />
0.91*<br />
12/13<br />
77<br />
82*<br />
0.69<br />
0.73<br />
*Historical figures differ from prior<br />
annual reports due to data improvements<br />
across all years.<br />
Average customer minutes<br />
without supply<br />
71<br />
68<br />
*Historical figures differ from prior<br />
annual reports due to data improvements<br />
across all years.