Construction and project management timeline<br />

■ May 2006<br />

General contractor bid solicitation: <strong>AFG</strong> invites general and<br />

main contractor Karl Steiner <strong>AG</strong> and other general contractors<br />

to submit bids.<br />

■ 23 rd June 2006<br />

Submission of general contractor bids:<br />

Negotiations and awarding process.<br />

■ Mid-July 2006<br />

Start of excavation, spearheaded by architects Gisel & Partner<br />

<strong>AG</strong>, Arbon.<br />

■ 14 th September 2006<br />

Contract between building sponsor and Karl Steiner <strong>AG</strong><br />

signed.<br />

■ 19 th September 2006<br />

First crane erected, perfect cooperation between general contractor<br />

and master builder, ARGE Stutz <strong>AG</strong>/Bressan Baut <strong>AG</strong>.<br />

■ 16 th Oktober 2006<br />

Laying of the foundation stone in the presence of district<br />

president Hans Peter Ruprecht and representatives of the<br />

municipalities of Arbon and Roggwil, heads of the council<br />

Martin Klöti (Arbon) and Werner Minder (Roggwil).<br />

■ 4 th May 2007<br />

Topping-out ceremony: Shell erected in only six<br />

and a half months.<br />

■ May – September 2007<br />

Shell installations, HVAC, facade.<br />

■ September – November 2007<br />

Finishing work and completion.<br />

■ 16 th November 2007<br />

Final acceptance and fi rst phase of move into<br />

new offi ce building.<br />

■ 19 th December 2007<br />

Shift to new location concluded.<br />

«Completing the construction in such a short<br />

period of time was a logistical challenge.»<br />

Thomas Hüberli, Karl Steiner <strong>AG</strong><br />

■ 21 st December 2007<br />

Celebration of completed building project, meal at<br />

the recently completed «Arboneria», the <strong>AFG</strong> Corporate<br />

Center’s staff restaurant.<br />

■ December 2007 – February 2008<br />

Finishing touches, outdoor area design.<br />

■ 28 th /29 th February 2008<br />

Offi cial opening of the <strong>AFG</strong> Corporate Center<br />

in the presence of guests.<br />

<strong>AFG</strong> Corporate Center | 9