CM December DECEMBER 2018
THE CICM MAGAZINE FOR CONSUMER AND COMMERCIAL CREDIT PROFESSIONALS
THE CICM MAGAZINE FOR CONSUMER AND COMMERCIAL CREDIT PROFESSIONALS
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
OPINION<br />
AUTHOR – Peter Walker<br />
On the facts in front of her Joanna<br />
Smith QC, in her judgment in January<br />
<strong>2018</strong>, rejected the contention that the<br />
arbitrator had failed to apply the rules<br />
of natural justice. The parties had, for<br />
example, made submissions regarding<br />
the Memorandum of Understanding.<br />
There were other considerations, and<br />
the adjudicator had furthermore posed<br />
specific questions to the parties, who<br />
had the opportunity to answer. Part 8<br />
Procedure was not appropriate in a claim<br />
including disputed facts.<br />
WINDING UP OR WIND-UP<br />
The adjudication debt, however, as<br />
ordered by Joanna Smith QC was unpaid<br />
in February <strong>2018</strong>, so the contractor<br />
petitioned to wind up the employer.<br />
The employer applied in the Chancery<br />
Division of the High Court, to strike out<br />
the petition. Morgan J in the resulting<br />
case In re Victory House General Partner<br />
Ltd [<strong>2018</strong>] 3 WLR 1024 noted that there was<br />
other litigation, not about the judgment<br />
debt, but about a liability to make a<br />
further payment under the contract.<br />
The contractor, for example, had made<br />
an application for a further payment of<br />
around £3 million, and the absence of any<br />
payment resulted in another adjudication.<br />
The adjudicator significantly decided that<br />
the value of the work done was around £7<br />
million, but that the contractor had been<br />
paid around £8.5 million, i.e. there had<br />
been an overpayment.<br />
This did not end the dispute, because<br />
the employer, not the contractor, initiated<br />
a third arbitration. It claimed that there<br />
were defects in the work.<br />
Morgan J considered this background<br />
to the contractor’s winding-up petition.<br />
He noted that, if the employer paid<br />
the judgment debt resulting from the<br />
first arbitration, it would have a crossclaim<br />
against the contractor due to the<br />
overpayment found by the adjudicator in<br />
the second arbitration.<br />
He turned for guidance to the decision<br />
of Coulson J in Grove Developments Ltd<br />
v S&T (UK) Ltd [<strong>2018</strong>] EWHC 123 (TCC).<br />
This case concerned the construction<br />
of a new hotel at Heathrow Terminal 4.<br />
There was a completion date of October<br />
2016, but the project was not ready until<br />
March 2017. There were three subsequent<br />
adjudications. The first decided that a<br />
Schedule of Amendments was part of the<br />
contract. The second decided that the<br />
contractor was entitled to an extension<br />
of time, but only until January 2017. The<br />
third arose from the employer’s pay-less<br />
notice in response to the contractor’s<br />
application for a stage payment. This is<br />
important to credit management, because<br />
if an employer does not serve such a notice<br />
on time, it is deemed to have accepted<br />
the valuation. This is known as a smashand-grab<br />
claim, whereby a contractor<br />
claims payment of the sums in their<br />
interim application without regard to the<br />
employer’s assessment as to its validity.<br />
The third arbitration concluded that it was<br />
not entitled to do so with the result that<br />
the contractor was entitled to £14 million.<br />
The employer finally started a Part<br />
8 Application, but Coulson J ruled that<br />
the pay-less notice was effective. It was<br />
accompanied by a spreadsheet detailing<br />
the sum to be paid. Coulson J added<br />
that upon payment the employer could<br />
apply for an adjudication of the true sum<br />
due. It could then make a claim for any<br />
consequent financial adjustment.<br />
NO SHORT CUTS<br />
There are consequently no short cuts when<br />
the other party has what Nourse LJ in the<br />
Court of Appeal described as ‘a genuine<br />
and serious cross-claim’. He did not have<br />
to deal with a Part 8 Application, but he<br />
was considering an undisputed debt case<br />
In re Bayoil SA [1999] 1 WLR 1471. Bayoil<br />
had chartered a tanker, but there were<br />
problems with the tanker’s engines and<br />
with the voyage generally. There were<br />
disputes resulting in an arbitration, and<br />
the ship’s owner was awarded over $1<br />
million. When there was a subsequent<br />
petition to wind up Bayoil, it did not<br />
dispute the debt, but its counterclaim<br />
exceeded the awarded amount.<br />
Nourse LJ proceeded cautiously, and he<br />
pointed out the potentially serious effects<br />
of a winding-up order. It was ‘draconian’,<br />
and if it was wrongly made, a company<br />
would have little chance of revival.<br />
Morgan J in the Victory House case<br />
followed this reasoning. The amount<br />
awarded by the adjudicator was not<br />
disputed, but the employer had a<br />
substantial bona fide cross-claim based<br />
on the alleged overpayment. The judge<br />
therefore dismissed the winding-up<br />
petition.<br />
A victory for law and common sense!<br />
A Part 8 Application or winding-up<br />
petition can be the correct procedure<br />
after the award of an undisputed and<br />
unpaid judgment debt, but there are no<br />
procedural short cuts if the debtor has a<br />
justifiable cross-claim. Where there are<br />
complicated building and other contracts<br />
involving stage payments, credit managers<br />
must monitor them carefully.<br />
Peter Walker is a freelance business<br />
writer.<br />
The Recognised Standard / www.cicm.com / <strong>December</strong> <strong>2018</strong> / PAGE 25