22.11.2018 Views

CM December DECEMBER 2018

THE CICM MAGAZINE FOR CONSUMER AND COMMERCIAL CREDIT PROFESSIONALS

THE CICM MAGAZINE FOR CONSUMER AND COMMERCIAL CREDIT PROFESSIONALS

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

OPINION<br />

AUTHOR – Peter Walker<br />

On the facts in front of her Joanna<br />

Smith QC, in her judgment in January<br />

<strong>2018</strong>, rejected the contention that the<br />

arbitrator had failed to apply the rules<br />

of natural justice. The parties had, for<br />

example, made submissions regarding<br />

the Memorandum of Understanding.<br />

There were other considerations, and<br />

the adjudicator had furthermore posed<br />

specific questions to the parties, who<br />

had the opportunity to answer. Part 8<br />

Procedure was not appropriate in a claim<br />

including disputed facts.<br />

WINDING UP OR WIND-UP<br />

The adjudication debt, however, as<br />

ordered by Joanna Smith QC was unpaid<br />

in February <strong>2018</strong>, so the contractor<br />

petitioned to wind up the employer.<br />

The employer applied in the Chancery<br />

Division of the High Court, to strike out<br />

the petition. Morgan J in the resulting<br />

case In re Victory House General Partner<br />

Ltd [<strong>2018</strong>] 3 WLR 1024 noted that there was<br />

other litigation, not about the judgment<br />

debt, but about a liability to make a<br />

further payment under the contract.<br />

The contractor, for example, had made<br />

an application for a further payment of<br />

around £3 million, and the absence of any<br />

payment resulted in another adjudication.<br />

The adjudicator significantly decided that<br />

the value of the work done was around £7<br />

million, but that the contractor had been<br />

paid around £8.5 million, i.e. there had<br />

been an overpayment.<br />

This did not end the dispute, because<br />

the employer, not the contractor, initiated<br />

a third arbitration. It claimed that there<br />

were defects in the work.<br />

Morgan J considered this background<br />

to the contractor’s winding-up petition.<br />

He noted that, if the employer paid<br />

the judgment debt resulting from the<br />

first arbitration, it would have a crossclaim<br />

against the contractor due to the<br />

overpayment found by the adjudicator in<br />

the second arbitration.<br />

He turned for guidance to the decision<br />

of Coulson J in Grove Developments Ltd<br />

v S&T (UK) Ltd [<strong>2018</strong>] EWHC 123 (TCC).<br />

This case concerned the construction<br />

of a new hotel at Heathrow Terminal 4.<br />

There was a completion date of October<br />

2016, but the project was not ready until<br />

March 2017. There were three subsequent<br />

adjudications. The first decided that a<br />

Schedule of Amendments was part of the<br />

contract. The second decided that the<br />

contractor was entitled to an extension<br />

of time, but only until January 2017. The<br />

third arose from the employer’s pay-less<br />

notice in response to the contractor’s<br />

application for a stage payment. This is<br />

important to credit management, because<br />

if an employer does not serve such a notice<br />

on time, it is deemed to have accepted<br />

the valuation. This is known as a smashand-grab<br />

claim, whereby a contractor<br />

claims payment of the sums in their<br />

interim application without regard to the<br />

employer’s assessment as to its validity.<br />

The third arbitration concluded that it was<br />

not entitled to do so with the result that<br />

the contractor was entitled to £14 million.<br />

The employer finally started a Part<br />

8 Application, but Coulson J ruled that<br />

the pay-less notice was effective. It was<br />

accompanied by a spreadsheet detailing<br />

the sum to be paid. Coulson J added<br />

that upon payment the employer could<br />

apply for an adjudication of the true sum<br />

due. It could then make a claim for any<br />

consequent financial adjustment.<br />

NO SHORT CUTS<br />

There are consequently no short cuts when<br />

the other party has what Nourse LJ in the<br />

Court of Appeal described as ‘a genuine<br />

and serious cross-claim’. He did not have<br />

to deal with a Part 8 Application, but he<br />

was considering an undisputed debt case<br />

In re Bayoil SA [1999] 1 WLR 1471. Bayoil<br />

had chartered a tanker, but there were<br />

problems with the tanker’s engines and<br />

with the voyage generally. There were<br />

disputes resulting in an arbitration, and<br />

the ship’s owner was awarded over $1<br />

million. When there was a subsequent<br />

petition to wind up Bayoil, it did not<br />

dispute the debt, but its counterclaim<br />

exceeded the awarded amount.<br />

Nourse LJ proceeded cautiously, and he<br />

pointed out the potentially serious effects<br />

of a winding-up order. It was ‘draconian’,<br />

and if it was wrongly made, a company<br />

would have little chance of revival.<br />

Morgan J in the Victory House case<br />

followed this reasoning. The amount<br />

awarded by the adjudicator was not<br />

disputed, but the employer had a<br />

substantial bona fide cross-claim based<br />

on the alleged overpayment. The judge<br />

therefore dismissed the winding-up<br />

petition.<br />

A victory for law and common sense!<br />

A Part 8 Application or winding-up<br />

petition can be the correct procedure<br />

after the award of an undisputed and<br />

unpaid judgment debt, but there are no<br />

procedural short cuts if the debtor has a<br />

justifiable cross-claim. Where there are<br />

complicated building and other contracts<br />

involving stage payments, credit managers<br />

must monitor them carefully.<br />

Peter Walker is a freelance business<br />

writer.<br />

The Recognised Standard / www.cicm.com / <strong>December</strong> <strong>2018</strong> / PAGE 25

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!