<strong>Asian</strong> <strong>Development</strong> <strong>Bank</strong> TA7343 Ho Chi Minh City MRT Line 2 Project<br />
MVA Asia Ltd <strong>Final</strong> <strong>Report</strong> – November 2010<br />
3.6.9 Using the demand forecasting models developed under TA4862, it is estimated that the total<br />
number of trips to be carried by public transport at the notional design years will be as shown<br />
in Table 3.4 (actual numbers for 2007 are included for comparison). These figures are very<br />
indicative, but provide a clear indication of the very important role of buses (and other public<br />
transport modes) as well as MRT in the future Transport Plan.<br />
Table 3.4 Public Transport Trip Forecasts<br />
Design<br />
Year<br />
Network Total MRT Daily<br />
Boardings<br />
3-10<br />
Total Bus Daily<br />
Boardings<br />
PT Mode<br />
Share<br />
2007 No MRT 0