JINNAH HYDROPOWER PROJECT<br />
Location The Project is located on right side of Jinnah Barrage<br />
on Indus River about 5 km downstream of Kalabagh<br />
Town and 234 km from Islamabad.<br />
Salient Features Installed Capacity<br />
Annual Energy<br />
Gross Head<br />
Design Discharge<br />
No. of Units<br />
Objectives<br />
96 MW<br />
688 GWh<br />
4.88 m<br />
2400 m 3 /sec<br />
8 units<br />
To Generate Electricity<br />
Consultants ACE (JV) NESPAK, NDC, & MWH. EASEPAK,DMC<br />
Contractor: M/s Dongfeng Electric Corporation (DEC) of China<br />
Date of Commencement as PC- I February 2006<br />
Date of Completion Actual/Revised<br />
Expected Dec 2012<br />
(Due to devastating effect of 2010 Flood the project completion<br />
will be delayed)<br />
Financial Status Local FEC Total (Rs. Million)<br />
Approved PC-I Cost 6,935.950 6,610.850 13,546.800<br />
Expenditures upto 30.6.2011 6,581.421 6,528.000 13,109.421<br />
PSDP Allocation 2011-2012 1,124.000 - 1,124.000<br />
Expenditure during the Month 6.650 - 6.650<br />
Current F/Y Expenditure 69.536 - 69.536<br />
Upto date Expenditure 6,650.957 6,528.000 13,178.957<br />
The Jinnah Hydropower Project is being financed through supplier’s credit. The utilization of Foreign Loan / supplier’s credit in above statement<br />
based on figures provided by the M/s. DEC China. However, there is no foreign loan utilization in Project Books and no IPC’s are submitted by the<br />
Contractor as it is an EPC / Turnkey basis Project.<br />
Physical Progress / Status<br />
PC-I for the Construction of O&M Staff Colony approved on 19.11.2009 for Rs. 253.07 m.<br />
Civil works of Powerhouse, Headrace & Tailrace Channels are almost completed. M/s DEC<br />
have conducted 72 hrs. reliability test at 2200 hrs. on 08.02.2012, but as per Consultants the<br />
same 72 hrs. reliability test will be conducted again as previously it was not conducted with<br />
maximum generation of 12 MW continuously. The first Unit has also been synchronized with<br />
National Grid.<br />
o Physical Progress 92.92 % against 97.50 %<br />
o Financial Progress *15.00 %<br />
*Being an EPC contract only mobilization advance of 15% has been paid to the contractor; Rest<br />
85% is arranged under supplier’s credit by the contractor.