LOCATION<br />
TRAPPI HYDROPOWER PROJECT<br />
The project area is located on the Sirran River near<br />
Trappi Village. The Project is 18 km from Mansehra<br />
in Khyber Pakhtunkhwa Province and about 160 km<br />
from Islamabad.<br />
SALIENT FEATURES<br />
Installed capacity 32 MW<br />
Mean Annual Energy 232 GWh<br />
Maximum gross head 171 m<br />
Dam height 146 m<br />
Dam Crest 450 m<br />
Reservoir Maximum<br />
Operating Level<br />
2600 ft<br />
Tentative Live Storage 200,000 Acre-ft<br />
Pressure pipe/tunnel 1500 m<br />
Design discharge 25 m 3 /s<br />
Plant factor 80.9%<br />
Feasibility Study 18 months<br />
PRESENT STATUS<br />
Project identified by Hydro Planning Organization (HPO), <strong>WAPDA</strong>.<br />
Reconnaissance study was carried out by HPO and Reconnaissance Report issued in May<br />
2010.<br />
Commitment for a grant of Euro 950,000 for financing the feasibility study of the project<br />
was made by KfW on 17 th January, 2011.<br />
Financial Agreement signed by KfW, <strong>WAPDA</strong> and Government of Pakistan on July 15,<br />
2011.<br />
TOR/EOI has been finalized and will be published in the Newspaper as soon as PC-II is<br />
approved.