BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)<br />
Location (District-wise) Nasirabad, Jaffarabad Districts of Balochistan and<br />
Jacobabad, Kambar-Shahdadkot Districts of Sindh<br />
Scope of work To provide the direly needed effluent disposal facilities<br />
for existing and proposed drainage projects, the work<br />
would increase crop production of agricultural land<br />
wasted due to ponds of water, increase in cropping<br />
intensity and environment condition will improve over<br />
Gross Commanded Area (GCA) of 287,106 hectares.<br />
EIRR 12.61%<br />
Donor Agency Govt of Pakistan<br />
Executing Agency <strong>WAPDA</strong><br />
Consultants -<br />
Contractor M/s Khyber Grace & M/s Ayub Brother<br />
Commencement Date July 2004<br />
Completion Date Actual June 2006 / Revised June 2012<br />
Financial Status Local FEC Total (Rs. Million)<br />
Approved PC-I Cost 4,485.200 - 4,485.200<br />
Expenditures upto 30.06.2011 3,924.512 - 3,924.512<br />
PSDP Allocation 2011-2012 1,000.000 - 1,000.000<br />
Expenditure during the Month - - -<br />
Current F/Y Expenditures 507.514 - 507.514<br />
Upto date Expenditure 4432.026 - 4432.026<br />
Reasons for delay<br />
o Physical Progress 73.00 % against 100 %<br />
o Financial Progress 98.81 % against 100 %<br />
The Revised PC-I amounting to Rs.6,536 million submitted to Ministry of Water & Power Islamabad on 08 th March, 2008.<br />
The torrential rainfall coupled with the historic floods during June July, 2010 have adversely affected the momentum / pace of the on going<br />
contract works, as the construction activities on almost all the contracts were suspended for about 4 to 6 months. In addition to the above,<br />
Law and Order situation particularly along the sites of the works awarded under Contract Nos. R-III (d/1) & R-III (d/2) have resulted in slow<br />
rate of progress. The work is suspended by the Contractor due to Financial Crunch and Flood 2010. The work is in progress on only Contract<br />
R-III(b/1)