CHASHMA RIGHT BANK CANAL PROJECT (LIFT-CUM-GRAVITY)<br />

1. LOCATION The proposed project is located on the right bank<br />

of Indus River in D.I. Khan District of NWFP.<br />

2. SALIENT FEATURES<br />

INTAKE Off takes from Head Race Channel<br />

of Chashma Hydropower Plant.<br />

FEEDER CANAL<br />

Capacity 2613 Cusecs<br />

Length 39 Miles<br />

F.S.L (at RD 04+000) 638.64 Ft<br />

Bed Level (at RD 404+000) 624.03 Ft<br />

PUMPING STATION<br />

Capacity 2533 Cusecs<br />

Lift 64 ft.<br />

Pumping Units 8 units<br />

Capacity 6 No of 353 cusecs each<br />

2 No of 212 cusecs each<br />

Type Vertical mixed flow pump<br />

MAIN CANAL (GRAVITY)<br />

Capacity 2533 Cusecs<br />

Length 73 Miles<br />

Command Area 286100 Acres<br />

F.S.L (at RD 0+000) 685.75 Ft<br />

Bed Level (at RD 0+000) 670.46 Ft<br />

DISTRIBUTARIES<br />

No. of Distributaries 25 Nos.<br />

Length 167 Miles<br />

Length of Minors 102 Miles<br />

PROJECT COST Rs. 61.066 Billion<br />

3. CURRENT STATUS<br />

Detailed Engineering & Tender Documents completed on Feb. 29, 2004 by M/s. NDC Joint Venture.<br />

PC-I (Rs.25.399 Billion) submitted to GOP/GONWFP for approval on July 31, 2004. Discussed in<br />

CDWP meeting held on 7.3.2005.<br />

PC-I amounting to Rs. 61.087 billion cleared in principle by CDWP in its meeting held on March 18,<br />

2010 for approval of ECNEC.<br />

A committee under Chairmanship of Deputy Chairman, Planning Commission was constituted to<br />

deliberate on the issues relating financing, engineering and economics of the Project.