RAINEE CANAL PROJECT<br />
Location Offtakes from left side of Guddu barrage Ghotki,<br />
Sukkur and Khairpur Districts of Sindh.<br />
Scope of Work<br />
Phase-I of Rainee Canal under taken currently.<br />
Agricultural production resulting in boost to economy,<br />
improvements in physical environment including<br />
atmosphere, climate, land and water, improvement in<br />
quality of life due to betterment in socio-cultural and<br />
socio-economic conditions.<br />
Salient Features Length of Main Canal<br />
Canal Capacity<br />
Length of Branches<br />
Distributaries and Minors<br />
Structures<br />
Command Area<br />
EIRR<br />
Execution by <strong>WAPDA</strong><br />
Consultants BARQAAB / TECHNO International<br />
175 km<br />
5155 cusecs<br />
609 km<br />
157 Nos<br />
Phase – I (107 Nos)<br />
412,400 acres<br />
Phase – I<br />
(113,690 acres)<br />
12%<br />
Contractors Friends Eng. Co. Ramzan & Sons, DESCON, SMC &<br />
SKB-KNK JV<br />
Date of Commencement October, 2002<br />
Date of Completion (Phase-I) Expected June 2011 / Rescheduled June 2012<br />
Financial Status Local Foreign Total (Rs. M)<br />
Approved PC-I Cost 18,862.000 - 18,862.000<br />
Phase-I Cost 6,279.000 - 6,279.000<br />
Expenditures upto 30.06.2011 9,717.081 - 9,717.081<br />
PSDP Allocation 2011-2012 1,500.000 - 1,500.000<br />
Expenditures during the month 14.502 - 14.502<br />
Current F/Y Expenditures 638.704 - 638.704<br />
Upto date Expenditures 10355.785 10355.785<br />
Phase-I<br />
o Physical Progress 92.00 % against 97.50 %<br />
The Revised PC-I amounting to Rs.32.392 billion has been forwarded by Secretary, Ministry of Water & Power Islamabad on 20 th Feb, 2010<br />
to Planning & Development Division Islamabad for obtaining approval of ECNEC. Revised Cost Phase-I Rs.16.837 Billion & Phase –II<br />
Rs.15.555 Billion.