Voltage test on the main<br />

circuits<br />

How to prepare the units<br />

Operations to be carried out on<br />

units not directly connected to<br />

the testing equipment<br />

76 - 07897542EN indice: D0<br />

Tests on <strong>site</strong><br />

After erection, the equipment shall be tested<br />

in order to check the correct installation.<br />

The power-frequency test voltage shall be<br />

80% of the rated test value (40<strong>kV</strong> rms),<br />

because the units have already been tested<br />

in <strong>Schneider</strong> <strong>Electric</strong> factory at 00% of the<br />

voltage rated value) and shall be applied<br />

to each phase conductor of the main circuit<br />

for minute earthing the other two phase<br />

conductors.<br />

The leads from the testing equipment shall<br />

be connected to the MV cable lugs of a unit.<br />

This requires the opening of a lower door<br />

during the test for passing the<br />

above-mentioned leads.<br />

For a complete description of the following<br />

operations, please consult the SF<br />

circuit-breaker instruction for use handbook.<br />

Warning<br />

This preparation entails the bypass of some<br />

interlock. Only appropriately trained staff<br />

shall be allowed to operate.<br />

The procedures described in the following<br />

shall be strictly applied.<br />

Voltage transformers and lightening<br />

arresters, if any, shall be disconnected<br />

during the voltage tests at power frequency<br />

in order to avoid severe damages.<br />

NB: In units equipped with VTs withdrawable<br />

fuse version, disconnect the fuses. In units<br />

equipped with fixed VTs, disconnect the VTs<br />

power supply primary circuit.<br />

CTs secondaries shall be short-circuited<br />

at the LV terminal boards (if the auxiliary<br />

circuits are open).<br />

During the voltage tests, all the unit shall be<br />

fitted with the relevant circuit-breakers.<br />

The circuit-breakers shall be plugged in<br />

service position and closed.<br />

Since hand closing is not permitted with<br />

closed doors, a special procedure is<br />

required (see below) when auxiliary power<br />

supply is not available.<br />

Obviously, the MV cables shall be<br />

disconnected and the earthing switch shall<br />

be opened.<br />

- Circuit-breaker in disconnected position<br />

and the compartment door open.<br />

- Lift the locking rod A located on the top of<br />

the circuit-breaker mechanism.<br />

- Insert spacer U to keep the rod in raised<br />

position.<br />

- Push the circuit-breaker to the service<br />

position and remove spacer U.<br />

- Charge the closing spring of the<br />

circuit-breaker and close it by pressing<br />

pushbutton “ I ”.<br />