6. Fuse box<br />
7. Downpipe for the <strong>pellets</strong><br />
8. Burner pipe<br />
9. Main pipe for the fuse cable<br />
Abbildung 12: Pellet <strong>boiler</strong><br />
Abbildung 13: Overview of the PL15 mechanism<br />
If the <strong>boiler</strong> has been fully connected to the heating system with both water and electricity supplies, the<br />
PL can be operated.<br />
At first, the pellet bin must be filled up. The filling is done by hand. We recommend that the bin should<br />
always be filled up to the top to ensure a good, long operation.<br />
The filling up of the pellet storage bin can also be done automatically with the aid of an optional external<br />
feeding facility. Further information about his can be found in our material.<br />
Important: The KUENZEL pellet <strong>boiler</strong> is equipped with an automatic fire pan ash–emptier. The ash–<br />
emptying cycle is introduced after each burn–out. If there’s no burn–out for a certain amount of time, the<br />