tends to be smoother in Latvia than in Estonia. Given the complexity of the local governmental<br />

approval process and its critical importance to the implementation of the project, successful<br />

completion of the detail planning phase is crucial for any development project.<br />

After the detail planning approval has been obtained, the next step is to prepare the building design<br />

documentation within the limits prescribed by the detail planning and additional architectural and<br />

construction requirements that the local authorities may prescribe for the project. Arco Investeeringud<br />

usually commissions the designs by the same architectural bureau that prepared the proposal for the<br />

detail planning. The building design documentation details the exact location of each building, floor<br />

plans and division of space and facades. The design documentation is needed for applying for a<br />

building permit for the project. The building permit issued by the local municipalities is needed before<br />

construction can be commenced, and it is granted on the basis of the design documentation. According<br />

to the management of Arco Investeeringud, the average time from the completion of the design<br />

documentation to obtaining a building permit is approximately six months.<br />

The building permit enables the Group to proceed to the construction phase. The Group’s key supplier<br />

in this project phase is the main contractor, which is selected through a tender process. The Group’s<br />

own construction division participates in the tendering alongside third-party contractors, and Arco<br />

Investeeringud will not choose it unless the offered price is competitive. On its recent larger<br />

development projects (e.g. Kolde) the Group has used Arco Ehitus as the main contractor and has not<br />

had to depend on external main contractors. After the tendering, the construction contract is finalised<br />

and signed, and the Group appoints its own supervisor for the project. Arco Investeeringud regularly<br />

supervises the project development and building documentation in the Group’s development projects.<br />

The general contractor prepares the records of the construction work and other documentation required<br />

by the relevant building acts and a draft for the construction contract.<br />

When the building work has been completed, the Group files an application with the local authorities<br />

for a permit for use, if the building is located in Estonia or for an act for commissioning of the<br />

building, if it is in Latvia. The building cannot be taken into use before the local government<br />

authorities have inspected it and issued the permit for use or executed the act for commissioning of the<br />

building.<br />

The time required by the construction phase has increased become longer over the last few years due<br />

to supply constraints in the construction market. The average building time for residential projects is<br />

currently approximately 12 months, and hotel projects take as long as 26 months.<br />

Under the terms of the construction contract, the main contractor gives a guarantee of construction<br />

works as to the quality of the workmanship and materials, the guarantee indicates, that the construction<br />

complies with the contract and that the construction is safe and fit for use. The guarantee is granted for<br />

a period of at least two years as of the date on which building is completed. The contractor must<br />

correct at his expense and within a reasonable period of time any construction faults or deficiencies<br />

that become evident during that period.<br />

The sales process is initiated when the building is substantially completed. Arco Investeeringud does<br />

not retain or manage the building itself unless it can see the potential to develop the property further.<br />

Both residential and non-residential development projects are sold either to investors or end-users at<br />

completion. A real estate agent is usually appointed at a relatively early stage and a marketing<br />

campaign is prepared and conducted concurrently with the construction phase. Arco Investeeringud<br />

often uses the services of Group’s own agency division because it is comfortable with its sales<br />

capability and familiar with its practices resulting in a professional and faster solution intra-group.<br />

Sales costs constitute up to two per cent of the total development project expenses. When willing<br />

buyers have been found, sales contracts concluded and completed, this concludes the development<br />

process.<br />