The consultants developed seven concepts for the <strong>City</strong> <strong>of</strong> <strong>Alexandria</strong> to consider for various<br />

areas throughout the city.<br />

Project Costs<br />

The Opinion <strong>of</strong> Probable Cost (OPC) shown on the following slides includes:<br />

• Pool structure, equipment, and enclosure (indoor)<br />

• Support Spaces<br />

• Entry<br />

• Locker rooms<br />

• Storage/Mechanical<br />

• Office Space<br />

• Site Construction Cost ($25 per sq. ft.)<br />

• FF&E<br />

• 5% inflation<br />

• 10% contingency<br />

• Indirect costs for A&E, surveys, permitting, etc.<br />

• The OPC is based on local labor and material costs<br />

• The OPC does not include Land Acquisition, Demolition, or Un-anticipated<br />

environmental concerns<br />