OPINION OF PROJECT COST: OPTION 3<br />
Description Unit Amount Opinion <strong>of</strong> Cost<br />
Bathhouse 6,330 $1,425,281<br />
Lobby Sq. Ft. 100<br />
Managers Office Sq. Ft. 125<br />
Guard Room / First Aid Sq. Ft. 100<br />
Pool Mechanical Sq. Ft. 1,400<br />
Building Mechanical Sq. Ft. 200<br />
Storage Sq. Ft. 700<br />
Locker Rooms Sq. Ft. 2,100<br />
Family Changing Room (2) Sq. Ft. 150<br />
Snack Bar Sq. Ft. 400<br />
Efficiency Sq. Ft. 1,055<br />
Aquatics 14,100 $3,813,500<br />
Recreation Pool Sq. Ft. 9,200 $2,185,000<br />
Recreation Ammenties Allowance 1 $500,000<br />
Lap Pool (8 Lane 25 Yard) Sq. Ft. 4,200 $971,250<br />
Springboad diving Quantity 2<br />
Tot Pool Sq. Ft. 700 $131,250<br />
Play Features Allowance 1<br />
Pool Heater Quantity 1<br />
Support $638,363<br />
Outdoor Deck Sq. Ft. 35,250<br />
Fence Linear Ft. 900<br />
Overhead Lighting Sq. Ft. 55,680<br />
Shade Structures Quantity 8<br />
Total Building Construction Costs 62,010 $5,877,144<br />
Site Construction Costs (parking lot, landscaping, utilities, walks) $1,550,250<br />
.<br />
Furnishings and Equipment Allowance $249,000<br />
Subtotal $7,676,394<br />
Inflation (1 year) 5% $383,820<br />
Contingency 10% $806,021<br />
Indirect Costs 10% $886,623<br />
Total Estimated Project Costs: $9,752,858<br />
Say $9,760,000<br />
Source: Counsilman-Hunsaker<br />