OPINION OF PROJECT COST: OPTION 5<br />
Description Unit Amount Opinion <strong>of</strong> Cost<br />
Public Spaces 5,200 $1,470,000<br />
Lobby Sq. Ft. 900<br />
Control / Cashier Sq. Ft. 150<br />
Guard Room / First Aid Sq. Ft. 150<br />
Concession/Kitchen Area Sq. Ft. 400<br />
Restrooms M/W Sq. Ft. 500<br />
Locker Rooms Sq. Ft. 2,100<br />
Team Locker Rooms Sq. Ft. 700<br />
Family Changing Room (2) Sq. Ft. 300<br />
Aquatic Center 24,650 $8,477,250<br />
25 Meter by 25 Yard Pool Sq. Ft. 6,200<br />
Springboard Diving Quantity 2<br />
Competitive Natatorium Sq. Ft. 12,000<br />
Leisure Pool (3 lanes) Sq. Ft. 3,400<br />
Play Feature Allowance 1<br />
Current Channel Add. Cost 1<br />
Waterslide Quantity 1<br />
Leisure Pool Natatorium Sq. Ft. 8,000<br />
Balcony Seating (500 seats) Sq. Ft. 3,000<br />
Pool Mechanical Room Sq. Ft. 1,650<br />
Building Support 2,630 $580,000<br />
Building Mechanical Sq. Ft. 1,900<br />
Electrical Sq. Ft. 500<br />
Janitor Sq. Ft. 50<br />
Elevator Sq. Ft. 80<br />
Elevator Machine Sq. Ft. 100<br />
Efficiency 6,496 $974,400<br />
Circulation and Walls (20%) Sq. Ft. 6,496<br />
Unit Sq. Ft. Opinion <strong>of</strong> Cost<br />
Total Building Construction Costs 38,976 $11,501,650<br />
Site Construction Costs $779,520<br />
.<br />
Furniture, Fixtures, Equipment $234,000<br />
Subtotal $12,515,170<br />
Inflation (1 year) 5% $625,759<br />
Contingency 10% $1,314,093<br />
Indirect Costs 10% $1,445,502<br />
Opinion <strong>of</strong> Probable Cost $15,900,523<br />
Say $15,901,000<br />
Source: Counsilman-Hunsaker<br />