The Community Liaison Information Group will meet quarterly to discuss the project and to<br />
allow for members to ask questions and to be briefed on ongoing work. The meetings are open<br />
to the public and include representatives from the project’s managing parties - VDOT and the<br />
National Park Service, as well as staff from <strong>City</strong> <strong>of</strong> <strong>Alexandria</strong>. Members <strong>of</strong> the Liaison Group<br />
have been identified as direct points <strong>of</strong> contact for gathering information on neighborhood<br />
concerns or questions, and will have direct contact to VDOT to address such items as they arise.<br />
ADDITIONAL & FOLLOW-UP INFORMATION<br />
Information regarding Jones Point Park construction is continuously updated on <strong>Alexandria</strong>’s<br />
Recreation, Parks & Cultural Activities department website at http://alexandriava.gov/recreation<br />
and VDOT’s website for the Woodrow Wilson Bridge project at http://www.wilsonbridge.com/.<br />
These links include information regarding community meetings, construction updates and other<br />
information and resources including how citizens may stay informed by subscribing to E-News<br />
or other advisories. The Recreation, Parks & Cultural Activities website includes a continuously<br />
updated overview <strong>of</strong> construction activities for a three week look-ahead schedule <strong>of</strong> anticipated<br />
work. The June 09, 2011 “Construction Schedule at a Glance” is attached below.<br />
# # #