OPINION OF PROJECT COST: OPTION 6<br />
Description Unit Amount Opinion <strong>of</strong> Cost<br />
Aquatics 630 $370,875<br />
Splash Pad Sq. Ft. 630<br />
Interactive Play Features Allowance 1<br />
Filtration Vault Quantity 1<br />
Filtration Equipment Quantity 1<br />
UV Sanitizer Quantity 1<br />
Total Building Construction Costs 370,875<br />
Site Construction Costs (landscaping, utilities, walks) $15,750<br />
.<br />
Subtotal $386,625<br />
Inflation ( 2 year) 10% $38,663<br />
Contingency 10% $42,529<br />
Indirect Costs 12% $56,138<br />
Opinion <strong>of</strong> Probable Cost $523,954<br />
Say $524,000<br />
Source: Counsilman-Hunsaker<br />
Page 45