OPINION OF PROJECT COST: OPTION 6<br />

Description Unit Amount Opinion <strong>of</strong> Cost<br />

Aquatics 630 $370,875<br />

Splash Pad Sq. Ft. 630<br />

Interactive Play Features Allowance 1<br />

Filtration Vault Quantity 1<br />

Filtration Equipment Quantity 1<br />

UV Sanitizer Quantity 1<br />

Total Building Construction Costs 370,875<br />

Site Construction Costs (landscaping, utilities, walks) $15,750<br />

.<br />

Subtotal $386,625<br />

Inflation ( 2 year) 10% $38,663<br />

Contingency 10% $42,529<br />

Indirect Costs 12% $56,138<br />

Opinion <strong>of</strong> Probable Cost $523,954<br />

Say $524,000<br />

Source: Counsilman-Hunsaker<br />

Page 45