Staff Report - City of Alexandria
Staff Report - City of Alexandria
Staff Report - City of Alexandria
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Status or<br />
Priority<br />
Planning and Capital Projects<br />
Division Project Name Location/Sub~Project Notes Team % Complete Expected<br />
Completion<br />
Active Capital Projects Ft Ward Park ~ <strong>City</strong> Council work session held on March<br />
26 to discuss the recommendations <strong>of</strong> the<br />
Ad Hoc Advisory Group. Ongoing<br />
interdepartmental work on management<br />
planning. <strong>City</strong> Council approved funding<br />
for OHA in FY2012 for Phase II<br />
archaeology work. Funding for additional<br />
implementation is contignent funds for<br />
FY2012, including any funds for master<br />
planning<br />
Active Capital Projects Ramsey House<br />
Visitor's Center<br />
Garden<br />
Active Capital Projects Athletic Field<br />
Improvements<br />
Active Capital Projects Park Facilities<br />
(CFMP)<br />
Active Capital Projects Park Facilities<br />
(CFMP)<br />
Active Capital Projects Park Facilities<br />
(CFMP)<br />
Active Planning Park Facilities<br />
(CFMP)<br />
LD ~ ~<br />
~ Unscheduled Project. Garden Club <strong>of</strong><br />
<strong>Alexandria</strong> and PZ BAR <strong>Staff</strong> project.<br />
Project scoped only. Response letter from<br />
staff to be provided August 30. MOA to be<br />
developed with Garden Club upon receipt<br />
<strong>of</strong> additional materials. No activity this<br />
month.<br />
JL, RMK ~ TBD<br />
Ben Brenman - parking 16 new spots for field. Cost analysis<br />
performed by TES. Coordination <strong>of</strong> cost<br />
and construction underway.<br />
BC WP<br />
Colosanto drainage Site visit performed in early June.<br />
Anticipate engineering design in<br />
Summer/Fall, 2011.<br />
AC, RMK<br />
GW #1 field replacement Field replacement underway to coincide<br />
with ACPS re-asphalt <strong>of</strong> parking lot and<br />
running track.<br />
KW 1-Jun-2011<br />
Simpson Netting Quote received. Work being scheduled. KW<br />
Needs Analysis and<br />
Survey<br />
Surveys have been sent; follow up phone<br />
calls to be complete week <strong>of</strong> June 13.<br />
Responses and analysis to be received by<br />
beginning <strong>of</strong> July.<br />
Active Planning Open Space 1 & 7 East Del Ray Contract awarded to Avon, March 2011.<br />
Construction commenced May 30. Late<br />
summer delivery-August 15.<br />
Active Planning Open Space Four Mile Run<br />
Properties<br />
Active Planning Freedmen's<br />
Cemetery<br />
Active Planning ACPS/RPCA Hammond Middle<br />
School<br />
Active Planning ACPS/RPCA Patrick Henry<br />
Community School<br />
Park Plan approved by PRC in March<br />
2011. Building interior and exterior<br />
painting completed as a part <strong>of</strong> Spring for<br />
<strong>Alexandria</strong> Day on May 6. Ribbon cutting<br />
held on May 15. Building open to the<br />
public on June 1.<br />
` Final site plan #3 and 95% contract<br />
documents with review ongoing.<br />
Construction start anticipated in<br />
Spring/Summer 2012.<br />
DW, LD 10% 1-Apr-2011<br />
JL, LD `5%CA `Late<br />
Summer<br />
2011<br />
LD ` `<br />
LD RMK Construction<br />
Documents<br />
November,<br />
2012<br />
Synthetic Turf Field, walking track and RMK DW Project started 2011~12<br />
field lights. Public meeting held 4/26 to<br />
discuss lights SUP. Approved at Planning<br />
Commission public hearing on June 7. <strong>City</strong><br />
Council public hearing on June 25. Turf to<br />
be installed (with or without lights in<br />
summer 2011)<br />
August 2010<br />
Modular classroom final site plan underway RMK DW complete Fall, 2013<br />
March 17, 2011 2